INSP-Final Inspection | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
jon Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/4/2020 | 2/5/2020 | 2/4/2020 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Jonathan LaFond Inspection cancelled from web by: Jonathan LaFond
|
INSP-Sprinkler Rough-in | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for All Valley scope of work is complete, scope of work is approved for cover at contractors discertion. Will need to verify calculations to support more than 1 head off of 1 inch piping, numerous areas throughout the existing section of tenant space have more than 1 head off of 1 inch pipe and approved plans show only 1 head off of 1 inch piping, corrections may be required. Need to verify compatibility between concelaed fusible link heads and the 155 quick response glass bulb heads, concealer heads are shown as 155 quick response heads on city approved drawings. A seperate rough in inspection will be required before final inspection to verify more than 1 head off of 1 inch piping as well as concealed/recessed head compatability.
peyton Phone #: ###-####
|