Information based on query as of Sunday, May 12, 2024.
Permit Information
Permit NumberGRD17-00025
StatusFinaled
Name STEED CONSTRUCTION
Site Address 555 S COLE RD
Project NameIntermountian Gas Grading
Customer Number 
ePlanReviewYes
Description
(Intermountain Gas) Permit to excavate, grade, and pave a parking lot per engineered plans on file as approved by Public Works Department. Scope of work includes four phases of work as approved on plans provided. Install curbing, landscaping, site lighting improvements & striping as noted on plans. No buildings are to be constructed or installed under this permit. Reference CFH17-00029 & DRH17-00258 for planning/zoning approval // (C_P)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection9/5/20189/5/20189/5/2018PPASS
DetailsTroy Cobbley
Life safety passed


Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
FIRE-Final Inspection8/29/20188/30/20188/30/2018APART
DetailsTroy Cobbley
A temporary for life safety is being given until the fire hydrant issue is addressed. The issue is that there is currently marked parking in front of the fire hydrant. This parking needs to be designated no parking but needs to be approved by the Planning dept.


Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
GRD-Final8/29/20188/29/20188/29/2018PDONE
DetailsTiffany Lowery
GRD-Grading Inspection10/22/201710/23/201710/23/2017ACANC
DetailsDan Ediger
SHOULD HAVE BEEN CALLED ON THE PLUMBING PERMIT PLM17-03869 Jim Wellman

Requesting an inspection for 1500 gallon grease interceptor. Not sure what type of inspection is needed. I talked to Dan Ediger Plumbing inspector looked at it and need him to re-inspect tank. Phone #: ###-#### >> Inspection requested via web by Jim Wellman
GRD-Conference10/4/201710/4/201710/4/2017PPASS
DetailsMike Jordan
Jim Wellman Phone #: ###-####. Footing and stemwall for trash enclosure.