Final | 11/16/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Brian Scoles
|
|
|
final ok- card signed
|
Final | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PART |
Brian Scoles
|
|
|
Please call Lee 1/2 hr. before arrival to inspection. ###-####. Phone #: ###-#### Inspection requested via web by Bryan Palmer- single wall flue on water heater needs 6" clearance to sheetrock- mike taking care of this- Temp occupancy ok
|
Final | 7/24/2018 | 7/25/2018 | 7/25/2018 | P | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer- b vent needs 1" clearance at roof and to combustibles- need to support duct in approved method- talked with Mike onsite aboiut issues- ok for cover
|
Rough-in | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer - Bathroom exhaust not installed per approved plans, need 1" clearance from combustables on b-vent for water heater, Need to support spiral duct work in between joists on the mezzanine in a approved manor.
|
Pressure Test | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer - 20lb gas pass on piping to water heater
|