Final | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | PASS |
Brian Scoles
|
|
|
JOHN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- final ok
|
Final | 5/15/2019 | 5/15/2019 | 5/15/2019 | A | PART |
Brian Scoles
|
|
|
20lb gas pass from roof to 4 water heaters- drip legs on roof cannot be in contact with roof need to support- 2 of the water heaters have sediment traps before shutoff valves needs to be after- went over with contractor onsite
|
Final | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PART |
Brian Scoles
|
|
|
JOHN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- 60lb gas test roof from open tee to RTUs pass- need to see 20lb test on welded pipe to water heaters still
|
Final | 3/21/2019 | 3/21/2019 | 3/21/2019 | A | PART |
Brian Scoles
|
|
|
TCO for caffeteria and kitchen only ok- still need to test rest of gas line to locker rooms on roof
|
Pressure Test | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PART |
Brian Scoles
|
|
|
JOHN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- 60lb gas pass roof for RTUs- tagged meter gas piping- will need to test locker room to water heaters when roof is completed and gas is ran
|