Final | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Arielle Hendricks- final ok- card sighed
|
Final | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | PART |
Brian Scoles
|
|
|
need air balance report onsite- insulation ok- seal ok- ok for ceiling tiles- dryer vent exceeds max length so need to reroute went over with chuck insite- co system needs to be operational and working at final inspection- smoke detector need installed according to prints
|
Conference | 11/14/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Brian Scoles
|
|
|
discuss co louvers and fan- will install per our discussion
|
Rough-in | 9/29/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Krista Boss- R/I ok- seal on all duct ok- insulation ok ok for grid to be installed
|
Rough-in | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | NR |
Brian Scoles
|
|
|
Partial inspection. Make sure to call Aleks on way at ###-#### Phone #: ###-#### Inspection requested via web by Xanti Berria- will reschedule- still installing
|
Rough-in | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PART |
Brian Scoles
|
|
|
Please conduct a mastic inspection on the front half of the building as soon as possible today. Call Aleks ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- seal on duct work front section ok- ok to insulate- need revised drawings onsitew by next inspection- need to add this mech permit to building permit by next inspection
|