Final | 12/14/2018 | 12/17/2018 | 12/17/2018 | A | PASS |
Jack Reynolds
|
|
|
final ok
|
Final | 12/13/2018 | 12/14/2018 | 12/14/2018 | P | CANC |
Jack Reynolds
|
|
|
Dale Phone #: ###-#### - not ready did not have the 5lb flue gauge ready rescheduled for monday morning
|
Pressure Test | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Jack Reynolds
|
|
|
Dale Phone #: ###-#### - 20lb gas pressure test ok- tagged meter bar
|
Rough-in | 8/24/2018 | 8/28/2018 | 8/28/2018 | A | PART |
Jack Reynolds
|
|
|
Dale Phone #: ###-####- Partial R/I supply and return runs downstairs and upstairs are ok- Hvac contractor needs an ok for insulation and sheet rock in mech room so he can finish his R/I - also need to see gas line pressure test and flue pressure test
|
Pressure Test | 8/24/2018 | 8/28/2018 | 8/28/2018 | A | CANC |
Jack Reynolds
|
|
|
Dale Phone #: ###-####- no pressure test yet
|