Final | 5/23/2019 | 5/24/2019 | 5/24/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - final ok signed occ card
|
Final | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - temp final ok
|
Final | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | NR |
Jack Reynolds
|
|
|
Inspection requested via web by Oleg Chervak - 4 units still need air balanced and all reports need to be onsite in each unit
|
Final | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | NR |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak
|
Rough-in | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Jack Reynolds
|
|
|
3 FLOOR Phone #: ###-#### Inspection requested via web by Oleg Chervak - R/I for 2nd floor and 3rd floor ok buidling D
|
Rough-in | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | NR |
Jack Reynolds
|
|
|
PAR 2 FLOOOR Phone #: ###-#### Inspection requested via web by Oleg Chervak - talked with montey and he said they are not finished and it wouldn't pass yet - not ready
|
Rough-in | 12/6/2018 | 12/7/2018 | 12/7/2018 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak -2nd floor SE unit needs duct seal -2nd floor NW unit duct work not finished and needs duct seal -2nd floor NE needs duct seal in the hallway and mech room
|
Rough-in | 12/6/2018 | 12/6/2018 | 12/6/2018 | P | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - 1st floor only R/I ok- duct seal ok - 2nd floor needs some duct seal finished and duct work that penetrated the ceiling needs to be moved - 3rd floor needs duct work penetrating ceiling moved to wall
|
Rough-in | 11/26/2018 | 11/27/2018 | 11/27/2018 | A | CANC |
Jack Reynolds
|
|
|
PARTIAL Phone #: ###-#### Inspection requested via web by Oleg Chervak
|
Rough-in | 10/19/2018 | 10/19/2018 | 10/19/2018 | P | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- partial R/I for pre rock so that soffits can be framed and duct work can be ran- This partial is on dryer vents and and exhaust ducting- still need to see dryer installation instruction- its being said that the dryers being installed have the ability to run 120 ' for one model and 200 ' for another model i did see an email chain back and forth from GE and owners on this topic-
|
Rough-in | 10/9/2018 | 10/10/2018 | 10/10/2018 | A | NR |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- not ready- need to see nail plates on dryer exhuast and a few linesets- also need to see specs on dryer for the first floor because lengths will be longer than 35'- R/I will be a partial so dry wall can be installed on ceiling for fire rating- equipment will set near final aswell
|