Final | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PASS |
Brian Scoles
|
|
|
Melo site contact. Phone #: ###-#### Inspection requested via web by RM Mechanical- final ok
|
Rough-in | 10/8/2019 | 10/9/2019 | 10/9/2019 | P | PART |
Jack Reynolds
|
|
|
Site Contact - Mark Hammer Phone #: ###-#### Inspection requested via web by RM Mechanical - duct seal R/I phase3 area B ok
|
Rough-in | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Chad Schwendiman
|
|
|
Jason Davidson site contact Phone #: ###-#### Inspection requested via web by RM Mechanical - Phase 2 okay
|
Rough-in | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | PART |
Brian Scoles
|
|
|
Please contact Jason Davidson at least 30 minutes before arrival. Phone #: ###-#### Inspection requested via web by RM Mechanical- ok for ceiling tiles excluding tiles where sound boots will be installed- went over with Jason onsite- recall in when boots are installed
|
Rough-in | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PART |
Brian Scoles
|
|
|
Partial rough in. Jason Davidson site contact Phone #: ###-#### Inspection requested via web by RM Mechanical- seal on all ducts ok- supply registers ok- need sound boots installed in grid to ok to cover with ceiling tiles- call in when ready
|
Rough-in | 5/20/2019 | 5/20/2019 | 5/20/2019 | P | PART |
Brian Scoles
|
|
|
Trever Jensen site contact. Phone #: ###-#### Inspection requested via web by RM Mechanical- 2 bathroom seal on duct ok- ok to sheetrock lids
|
Rough-in | 3/1/2019 | 3/1/2019 | 3/1/2019 | P | PASS |
Brian Scoles
|
|
|
Temporary occupancy for phase 1. Site contact Trever Jensen Phone #: ###-#### Inspection requested via web by RM Mechanical- temp occupancy ok for phase 1
|
Rough-in | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | PASS |
Brian Scoles
|
|
|
Cover inspection. Bill Burch site contact. Phone #: ###-#### Inspection requested via web by RM Mechanical- R/I ok- ok for ceiling tiles- Made Bill aware of condensate pump off fan coil not attached- will get with plumbers to verify before cover
|
Rough-in | 1/29/2019 | 1/29/2019 | 1/29/2019 | P | PART |
Brian Scoles
|
|
|
Trever Jensen site contact. Phone #: ###-#### Inspection requested via web by RM Mechanical- seal on all duct ok- registers and flex ok- ok to install ceiling tiles all areas except for lobby front area- recall in when ready
|
Rough-in | 1/16/2019 | 1/17/2019 | 1/17/2019 | A | PART |
Brian Scoles
|
|
|
Bill Burch site contact Phone #: ###-#### Inspection requested via web by RM Mechanical- seal on duct work above 2 bathrooms east side ok- bathrooms are going to change to grid ceiling- need to provide return air path sheetrocked all the way to ceiling-
|
Rough-in | 12/28/2018 | 1/2/2019 | 1/2/2019 | A | PART |
Brian Scoles
|
|
|
Trever Jensen site contact. Partial rough-in inspection. Phone #: ###-#### Inspection requested via web by RM Mechanical- seal on duct in toilet 104 ok- ok for sheetrock this bathroom only- FCU 11 will be relocated per RFI thats above bathroom to grid ceiling area
|
Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | FAIL |
Brian Scoles
|
|
|
Partial rough in Phone #: ###-#### Inspection requested via web by RM Mechanical- need city approved drawings onsite to do inspection- none could be found- seal on misc duct ok
|