Permit NumberMEC19-03993
StatusFinaled
Name BAUER HEATING & AIR COND
Site Address 3650 S MILLBROOK WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
New: HVAC Install
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final11/25/201911/25/201911/25/2019PPASS
DetailsEric Strole
inspector can go any time during day, all corrections are complete. Please call me if you have any questions. Thank You, Tom Phone #: ###-#### Inspection requested via web by Tom Bratcher
Final11/22/201911/22/201911/22/2019PNR
DetailsEric Strole
Inspector can go to site any time throughout day, it is ready. Thank You Phone #: ###-#### Inspection requested via web by Tom Bratcher-Have not received balance report as discussed at last inspection. When balance report is sent to Chad call back in for final.
Final11/21/201911/21/201911/21/2019PPART
DetailsChad Schwendiman
Tom Bratcher will be on-site to go over inspection with mechanical inspector. Thank You Phone #: ###-#### Inspection requested via web by Tom Bratcher - Temporary occupancy okay. Need to patch aramflex in east side mechanical room, Need email from Air balancer stating economizer is fuctioning per engineers design.
Rough-in11/12/201911/12/201911/12/2019PPART
DetailsEric Strole
Please contact Tom Melton at jobsite and he will show you what we need for inspection. We are looking to insulate ductwork in the mechanical rooms. Thank You Phone #: ###-#### Inspection requested via web by Tom Bratcher-Ok to insulate ducts in 2nd mechanical room.
Conference11/7/201911/8/201911/8/2019ADONE
DetailsChad Schwendiman
Please ask for tom on the jobsite. Phone #: ###-#### Inspection requested via web by Tom Bratcher - Went by to go over the economizer set up.
Rough-in11/7/201911/7/201911/7/2019APART
DetailsEric Strole
Please ask for tom on the jobsite. This inspection will be for approval to insulate ductwork in the mechanical room Phone #: ###-#### Inspection requested via web by Tom Bratcher-OK to insulate west side mechanical room.
Rough-in10/29/201910/30/201910/30/2019APASS
DetailsEric Strole
Please call Tom when on the way. This inspection is for approval to install ceiling tiles in the grid Phone #: ###-#### Inspection requested via web by Tom Bratcher-Above grid pass.
Rough-in10/14/201910/15/201910/15/2019PPASS
DetailsBen Livingston
Inspector please call Tom when on the way. You can come in morning or afternoon, whichever you prefer. Thank you Phone #: ###-#### Inspection requested via web by Tom Bratcher
- duct seal ok to insulate -
Rough-in9/18/20199/19/20199/19/2019APART
DetailsJack Reynolds
This inspection is rough for cover. Tom will be on site to meet with you. Thank you Phone #: ###-#### Inspection requested via web by Tom Bratcher
- R/I bathrooms hard lid cover only ok