Rough-in | 8/6/2020 | 8/7/2020 | 8/7/2020 | A | PASS |
Brian Scoles
|
|
|
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen- R/I ok- ok for ceiling tiles- couple places need flex supported and rerouted pinched off- talked with David onsite will fix
|
Rough-in | 7/16/2020 | 7/20/2020 | 7/20/2020 | A | PASS |
Brian Scoles
|
|
|
duct seal inspection Phone #: ###-#### Inspection requested via web by Brandon Sorensen- R/I ok- seal on all duct ok whole building- David will take pics of insulation above soffits- ok to cover soffits- ok for ceiling grid to install
|
Rough-in | 7/2/2020 | 7/7/2020 | 7/7/2020 | A | PART |
Brian Scoles
|
|
|
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen- 2 bathroom hard lids ok to cover
|
Rough-in | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | PART |
Brian Scoles
|
|
|
duct sealer inspection - call david Phone #: ###-#### Inspection requested via web by Brandon Sorensen- seal on all duct ok- will need to see supply and return mains off RTU 8 when installed- need verification on relief dampers in existing units if there being used or capped off- need hard lid inspection on restrooms
|
Rough-in | 5/13/2020 | 5/14/2020 | 5/14/2020 | A | PASS |
Brian Scoles
|
|
|
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen- R/I ok phase 1- ok for ceiling tiles-temp occupancy ok phase 1 lobby, conference and 2 offices- c line west existing no work registers remained
|
Final | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | CANC |
Brian Scoles
|
|
|
Final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- should have been sealer inspection- needs insulation installed- recall in for am inspection tomorrow to meet installer onsite Inspection cancelled from web by: Brandon Sorensen
|
Rough-in | 5/13/2020 | 5/13/2020 | 5/13/2020 | A | PART |
Brian Scoles
|
|
|
Final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- Seal on duct above grid ok- ok to insulate- need installer onsite with ladder to access above ceiling that has all ceiling tiles installed to verify registers and flex- talked with installer about meeting tomorrow at around 830- Do not install ceiling tiles at this time in areas that are open
|
Final | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | FAIL |
Brian Scoles
|
|
|
Final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- mechanical drawings need reviewed by mechanical plan reviewers with city- reschedule when ready
|
Rough-in | 4/15/2020 | 4/17/2020 | 4/17/2020 | A | FAIL |
Brian Scoles
|
|
|
cover inspection - call david Phone #: ###-#### Inspection requested via web by Brandon Sorensen- Need plan mod submited to city for HVAC work and have approved city prints onsite for this drawing- Memo style mechanical.pdf on approved drawings states these need reviewed and have never been submitted- reschedule when approved and onsite
|
Rough-in | 4/15/2020 | 4/16/2020 | 4/15/2020 | A | CANC |
Brian Scoles
|
|
|
Cover inspection - call david Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen Inspection cancelled from web by: Brandon Sorensen
|