BLD-Conference | 2/23/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Mike Jordan
|
|
|
Check status. End of 25 day notice.
|
DOC - Permit Finaled | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PASS |
Mike Jordan
|
|
|
Building permit has been issued.
|
BLD-Conference | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | FAIL |
Mike Jordan
|
|
|
25day notice issued. No effort has been made by owner to get permits.
|
BLD-Conference | 2/15/2018 | 2/22/2018 | 2/22/2018 | A | CANC |
Mike Jordan
|
|
|
Check on status. Issue 25 day notice.. rescheduled for 2-23 in the am.
|
BLD-Conference | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | DONE |
Mike Jordan
|
|
|
Per Mike Phone #: ###-####. Issued 5 day notice. A reinspection has scheduled to check on progress and issue 25 day notice.
|
MEC-Conference | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Alan Hauser
|
|
|
left notice on front door and sent picture to supervisor
|
ELE-Conference | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Tom Saunders
|
|
|
electrical work has been done without a permit...stop work order and correction notice posted...future inspection schedule for 1/4/18 unless permits are pulled and inspections scheduled
|
BLD-Conference | 12/21/2017 | 12/21/2017 | 12/21/2017 | A | FAIL |
Mike Jordan
|
|
|
Permits required for re-roof, interior remodel and window relacement. Correction notice and stop work issued. Also noted electrical, plumbing and mech. work beeing done with no permits. parcel hold and double fee building permit and all trades.
|