INSP-Final | 5/24/2016 | 5/25/2016 | 5/25/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Final | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | CANC |
Troy Cobbley
|
|
|
Tyler is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead Hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | FAIL |
Katie Marron
|
|
|
Hydrostatic test Fail. Will need to be recompleted.
Roughin completed satisfactory. Ok to cover. Verified upright sprinklers in concealed pocket spaces, 4 dry sidewalls, earthquake bracing and pipe sizes match resubmitted plans as noted from previous inspection. Additionally inspected pendant drops.
Minor items to be completed for Final: -Missing coverage at File room (pendant to be moved over) -revised set of plans onsite - remove tape from uprights in janitor rm and ensure they have not been painted
|
INSP-Supply line flush | 4/26/2016 | 4/27/2016 | 4/27/2016 | A | DONE |
Katie Marron
|
|
|
Underground flush
|
INSP-Supply line flush | 4/25/2016 | 4/26/2016 | 4/26/2016 | P | CANC |
Katie Marron
|
|
|
Should be under permit NAF15-00044. Rescheduled due to buried supply valve.
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2016 | 4/26/2016 | 4/26/2016 | P | CANC |
Katie Marron
|
|
|
Wrong permit number. Underground is NAF15-00044. Inspection input under that.
|
INSP-Final | 2/23/2016 | 2/24/2016 | 2/24/2016 | A | FAIL |
Troy Cobbley
|
|
|
Project is not ready for final as requested. Project is not ready for rough-in yet. Missing earthquake bracing, missing upright coverage in pockets at the main entry, pipe sizing of riser nipples and starter pieces do not match the approved plans, missing dry sidewall heads in the exterior pockets. I gave the general contractor the ok to cover hard lids as indicated on the plans. Resubmittals are required showing all changes such as piping size changes and the additional fittings used, and additional sprinkler heads.
|