INSP-Final | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | DONE |
Troy Cobbley
|
|
|
Permit finaled
|
DOC - Permit Finaled | | | 11/20/2017 | | DONE |
|
|
|
Doc Final Per Troy
|
INSP-Sprinkler Rough-in/Hydro | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | PASS |
Troy Cobbley
|
|
|
Hydro test passed and cage installed. Need insulation in crawl space to final.
|
INSP-Final | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | FAIL |
Troy Cobbley
|
|
|
Provide hydro test, provide cage for upright under stairs and provide the insulation in the crawl space.
|
INSP-Sprinkler Rough-in | 5/19/2017 | 5/22/2017 | 5/22/2017 | P | PASS |
Troy Cobbley
|
|
|
For todays inspection I verified that insulation had been installed at the deck above the sprinkler piping in the new area. Installation appeared adequate.
|
INSP-Final | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PART |
Scott Arellano
|
|
|
Ok to cover. Crawl space and roof overbuild areas with sprinkler protection to be tented and have acive heat sourced from warehouse and office areas. Final inspection will occur after finish is installed in office areas.
|