Final | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | PASS |
Daryl Spivey
|
|
|
East Building - if questions call Jesse @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
PLM-Aging Inspection | 6/20/2019 | 6/20/2019 | 6/20/2019 | | PASS |
Daryl Spivey
|
|
|
wip
|
Plumbing Rough-in | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Daryl Spivey
|
|
|
if questions call Jesse @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann east bld 122 and next 2 units north tested ok,,,,,,ds
|
Plumbing Rough-in | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PART |
Daryl Spivey
|
|
|
East Building (4 units) if questions call Jesse @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Hauman 114, 116, 118, 120 units passed rough in...........ds
|
Water and/or Sewer | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | PASS |
Matt Wrobel
|
|
|
main water line (east) if questions call Jeremy @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Water and/or Sewer | 2/25/2019 | 2/26/2019 | 2/26/2019 | P | NR |
Daryl Spivey
|
|
|
main water line inspection. If questions call Jeremy @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 2/7/2019 | 2/8/2019 | 2/8/2019 | P | PART |
Daryl Spivey
|
|
|
East Building - (4) Units ready for Rough-In inspection. If questions call Jesse @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | PART |
Daryl Spivey
|
|
|
EAST BUILDING - if questions call Jesse @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann 4 units south end of east bld...........ds
|
Water and/or Sewer | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PASS |
Daryl Spivey
|
|
|
Main water supply. If there are any questions please contact Jesse at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann water service tie in from outside bld to mech room tested ok..........ds
|
Groundwork | 7/2/2018 | 7/3/2018 | 7/3/2018 | P | PART |
Bill VanDegrift
|
|
|
If there are any questions please contact Tom P. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann test on the gw ok no plans yet proceed at your own risk
|
Groundwork | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | PART |
Bill VanDegrift
|
|
|
If there are any questions please contact Tom P. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann east building residential gw test ok, still need resubmitted plans showing trunkline instead of individual sewer services to each unit. Everyone seems to be working on getting the plans submitted.
|
Groundwork | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Daryl Spivey
|
|
|
If there are any questions please contact Tom P. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Groundwork | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Tom P. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann sewer line inside bld tested ok...........ds
|
Groundwork | 5/14/2018 | 5/15/2018 | 5/15/2018 | P | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Tom P. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann east side tested ok............ds
|