PLM99-03656
| Final | 1/7/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/07/2000 at 16:02:33. Contact: ###-####. Final ok.
|
PLM99-03786
| Plumbing Rough-in | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 07:42:31. Contact: ###-####. Water drop to restroom undersized part waste test ok.
|
PLM00-00013
| Plumbing Rough-in | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PASS |
|
|
###-####. R/I ok.
|
PLM99-03742
| Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PASS |
|
|
ken ###-####. Final ok.
|
PLM98-03510
| Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PASS |
|
|
###-####. Final ok.
|