BLD99-03635
| BLD-Foundation | 1/6/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | A | PASS |
|
|
###-#### pouring at 10:30
|
BLD99-01098
| BLD-Energy code compliance | 1/7/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | A | PASS |
|
|
mark ###-####
|
BLD99-02367
| BLD-Final | 1/7/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/07/2000 at 17:04:35. Contact: ###-####.
|
BLD99-02521
| BLD-Final | 1/9/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 01/09/2000 at 17:52:17. Contact: . Need mechanical and plumbing.
|
BLD99-02266
| BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 07:37:07. Contact: .
|
BLD99-02590
| BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 07:37:58. Contact: .
|
BLD99-03286
| BLD-Other | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 07:38:40. Contact: . Ext. shear.
|
BLD99-03397
| BLD-Framing/Rough-in | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | NR |
|
|
###-####. Need mechanical and energy package done, before calling in a frame insp.
|
BLD99-03734
| BLD-Footing | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PASS |
|
|
###-#### joe\\
|
BLD98-03910
| BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PART |
|
|
Pending engineers approval of special inspection report.
|
BLD98-03901
| BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PART |
|
|
Pending engineers approval of special inspection report.
|
BLD98-03909
| BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | PART |
|
|
Pending engineers approval of special inspection report.
|
BLD00-00008
| BLD-Footing | 1/10/2000 | 1/10/2000 | 1/10/2000 12:00:00 AM | P | NR |
|
|
early start okay permit-ted ###-####. Haven't started yet.
|