MEC01-00118
| Final | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PASS |
|
|
###-####
|
MEC01-00118
| Final | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PASS |
|
|
###-####
|
BLD00-01175
| BLD-Framing/Rough-in | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PART |
|
|
###-#### passed by 415 pervously dry wall nailled and taped nailled 4 inches oc . 1/10/2001 3:12:47 PM
|
MEC01-00070
| Pressure Test | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 15:24:19. Contact: . final ok 1/10/2001 2:41:00 PM
|
BLD00-02411
| BLD-Framing/Rough-in | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 20:12:06. Contact: ###-####. recieved truss joist info and will put it in your box 415 joist and lvl meet engineering submited framing ok for insulation. 1/10/2001 3:05:20 PM
|
BLD00-02949
| BLD-Footing | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | CANC |
|
|
Eric ###-#### Eric ###-#### 425 called and is on site will add insp. 1/10/2001 3:13:22 PM
|
BLD00-03605
| BLD-Framing/Rough-in | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
shear insp bob ###-#### shear insp c/n ok exterior ok for cover. 1/10/2001 3:37:54 PM
|
BLD00-03605
| BLD-Framing/Rough-in | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
shear insp bob ###-#### shear insp c/n ok exterior ok for cover. 1/10/2001 3:37:54 PM
|
BLD00-03590
| BLD-Other | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 16:21:12. Contact: ###-####. brace pannel at kitchen less than 48 inches wide / all others ok for nailling. 1/10/2001 4:48:14 PM
|
BLD00-01563
| BLD-Concrete | 1/8/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/08/2001 at 07:07:21. Contact: ###-####. placed with special insp. pending report. 1/9/2001 1:28:43 PM
|