BLD00-03334
| BLD-Foundation | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 15:33:45. Contact: ###-####.
|
BLD00-02770
| BLD-Footing | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 16:53:56. Contact: ###-####. crew is working on ftg bar spec insp will be on site to ck final and test conc. 1/10/2001 1:08:24 PM
|
BLD00-03008
| BLD-Framing/Rough-in | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | A | FAIL |
|
|
shear wall insp Stephen DeBenedetti ###-#### east wall needs more nails the rest of the house and garage ok 1/11/2001 10:19:24 AM
|
BLD00-03706
| BLD-Foundation | 1/8/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/08/2001 at 08:31:32. Contact: ###-####. foundation has already been poured 1/10/2001 1:55:29 PM
|
BLD00-03660
| BLD-Foundation | 1/9/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 17:53:03. Contact: ###-####. 1/10/2001 1:06:49 PM crew is still working on forms checked what they had up looks ok 1/10/2001 4:12:02 PM
|
BLD00-03468
| BLD-Energy code compliance | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2001 at 07:59:34. Contact: . need final on rough plumbing 1/10/2001 2:14:57 PM
|
BLD00-03175
| BLD-Foundation | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
###-#### Jim floor slab crew is working on slab spec insp will beon site tomorrow for final and test conc. 1/10/2001 2:30:14 PM
|
BLD00-03661
| BLD-Footing | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
###-#### crew is still working on laying out forms checked what they had looks ok 1/10/2001 4:10:28 PM
|
BLD00-03642
| BLD-Footing | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Lazaro ###-#### basement ftg only ok 1/10/2001 1:43:58 PM
|
BLD00-02949
| BLD-Footing | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 425 On 1/10/2001 3:31:02 PM crew used #4 bar plans call for 5 engineer ok to double 4bar
|
BLD00-02949
| BLD-Foundation | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 425 On 1/10/2001 3:34:59 PM crew is working on wall what they have in place is ok they are using #4 at 6inchs on center as per engin ok
|
BLD00-02949
| BLD-Foundation | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 425 On 1/10/2001 3:34:59 PM crew is working on wall what they have in place is ok they are using #4 at 6inchs on center as per engin ok
|
BLD00-02949
| BLD-Footing | 1/10/2001 | 1/10/2001 | 1/10/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 425 On 1/10/2001 3:31:02 PM crew used #4 bar plans call for 5 engineer ok to double 4bar
|