MIS05-00228
| FIR-Final | 1/10/2006 | 1/10/2006 | 1/10/2006 3:52:50 PM | P | PASS |
|
|
Life safety finaled
|
FIR05-00604
| INSP-Sprinkler Rough-in | 1/9/2006 | 1/10/2006 | 1/10/2006 3:21:28 PM | P | FAIL |
|
|
Provide through bolts for the earth quake bracing on the main level. Finish installing upright sprinkler heads in the overbuilds. The main overbuild needs one more upright head for correct coverage. The overbuilds need reinspection. Riser not inspected.
|
FIR05-00029
| INSP-Supply line flush | 1/10/2006 | 1/10/2006 | 1/10/2006 3:17:29 PM | P | PASS |
|
|
Underground supply line flush passed.
|
FIR05-00664
| INSP-Final Inspection | 1/9/2006 | 1/10/2006 | 1/10/2006 1:44:28 PM | P | CANC |
|
|
Per the electrician the mechanical systems are dismantled and non functional at this point. No inspection performed.
|
FIR05-00605
| INSP-Final Inspection | 1/10/2006 | 1/10/2006 | 1/10/2006 1:43:31 PM | P | FAIL |
|
|
Monitoring not set up. No tampers on the two control valves. Per notes plans need to be resubmitted for the additional valve.
|
FIR04-00684
| INSP-Sprinkler Rough-in/Hydro | 1/10/2006 | 1/10/2006 | 1/10/2006 12:36:17 PM | A | PART |
|
|
Above ground hydro tests passed. Sprinkler devices on wet sytem passed alarm inspection.
|
FIR05-00104
| INSP-Alarm Testing | 1/10/2006 | 1/10/2006 | 1/10/2006 11:52:07 AM | A | PART |
|
|
Today we tested the fire alarm panel itself and the interconnections between it and the NAC panels. We also tested were the smoke detectors over the panels. Also tested was the wet system tamper switches and flow switches for all floors. I found one duct smoke detector that needs relocated and the north fourth floor manual pull did not work.
|