BLD05-00633
| FIRE-Final Inspection | 1/9/2008 | 1/10/2008 | 1/11/2008 3:55:54 PM | A | PART |
|
|
The 6th, 7th and 8th floor life safety is complete. The 4th floor garden are needs the emergency light at the stairs repaired and the sprinkler head just inside of the stairway door provided with a canopy and the tape removed. The fire watch can be discontinued as per Dave Hanniman. The 9th floor life safety stills needs to be completed as well as the 2nd, 3rd, 4th and 5th floor tie ins.
|
FIR07-00697
| INSP-Sprinkler Rough-in | 1/9/2008 | 1/10/2008 | 1/10/2008 4:39:58 PM | P | PART |
|
|
Only the piping above the hard lid areas as marked on the plans is ok to cover. Per the sprinkler fitter the plans are being resubmitted with the installation changes. I started to do a rough-in inspection but found heads added in the attic space and the piping configuration changed. It appears that instead of 12 heads supplied by 2" piping there are now 15 heads supplied from the 2" supply. This was on the first line I looked at. The piping configuration was the issue in two of the only two areas I looked at. I stopped the inspection at this point. On the way out of the building I noticed that the building eaves are combustible concealed spaces that will require sprinkler protection as per NFPA 8.14 or at a minumum meet one of the 15 exceptions as listed in the same section. I left a correction notice with the job superintendant.
|
FIR07-00510
| FIR-Aging Inspection | 1/10/2008 | 1/10/2008 | 1/10/2008 1:03:17 PM | | NR |
|
|
life safety passed.
|
BLD07-02798
| FIRE-Final Inspection | 1/9/2008 | 1/10/2008 | 1/10/2008 12:58:55 PM | P | PASS |
|
|
life safety passed
|
FIR07-00766
| INSP-Supply line flush | 1/10/2008 | 1/10/2008 | 1/10/2008 12:47:45 PM | P | PASS |
|
|
Underground flush passed.
|
BLD08-00035
| FIRE-Final Inspection | 1/9/2008 | 1/10/2008 | 1/10/2008 11:50:13 AM | A | PASS |
|
|
Life safety passed.
|
BLD07-02745
| FIRE-Final Inspection | 1/9/2008 | 1/10/2008 | 1/10/2008 9:57:47 AM | A | CANC |
|
|
Phone #: ###-#### Internet Inspection Request from: larry hobbs
|
FIR08-00003
| INSP-Final Inspection | 1/9/2008 | 1/10/2008 | 1/10/2008 9:57:05 AM | A | PASS |
|
|
Permit finaled
|
FIR07-01006
| INSP-Final Inspection | 1/9/2008 | 1/10/2008 | 1/9/2008 2:42:00 PM | A | CANC |
|
|
dave Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
|