ESC13-00365
| DOC - Permit Finaled | 1/10/2014 | 1/10/2014 | 1/10/2014 2:03:49 PM | P | PASS |
|
|
House is complete and landscaped. No materials left on adjacent empty lot. Trailwinds Sub BMPs still installed while under development. No further ESC inspections required.
|
ESC13-00524
| General Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 1:45:13 PM | | PASS |
|
|
No construction activity at time of inspection. BMPs and hillside stabilization appears to be adequate dispite significant snow melt runnoff over past 2 days. No dirt or sediment blowouts onto roads. No corrections at this time.
|
ESC13-00586
| Aging Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 1:43:37 PM | | PASS |
|
|
Finaled.
|
ESC13-00082
| Site Preparation | 1/10/2014 | 1/10/2014 | 1/10/2014 1:43:08 PM | P | PASS |
|
|
Make-up inspection from 1/9/14 - not a site prep inspection. House is nearly complete, driveway installed. Yard not yet landscaped, nor hills stabilized. Silt fence perimeter BMP in acceptable condition. No track out or runoff onto Cartwright observed.
|
ESC13-00586
| DOC - Permit Finaled | 1/10/2014 | 1/10/2014 | 1/10/2014 11:50:26 AM | P | PASS |
|
|
House complete, landscaped and occupied. BLD permit already finaled. No outstanding ESC issues.
|
ESC12-00147
| General Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 11:30:40 AM | | PASS |
|
|
Construction materials still on-site. No violations observed. Talked to WWTP contact Rob Anderson on-site and he confirmed that BLD final and ESC final will be called in January/early February. Minor interior work ongoing.
|
ESC13-00537
| Random Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 11:28:33 AM | P | PASS |
|
|
Stockpiles contained within silt fence perimeter. No trackout to surrounding areas at WWTP observed and no track out to Joplin.
|
ESC12-00023
| General Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 10:40:47 AM | | PASS |
|
|
Stabilization still in progress.
|
ESC13-00230
| Conference | 1/10/2014 | 1/10/2014 | 1/10/2014 10:31:16 AM | A | DONE |
|
|
Meet Brighton Corp. Danial on-site during inspection rounds.
1. Re-inspection fee will be paid today 2. Containment berms and wattles will be installed at areas where runoff occured. 3. Drop inlet bags have already been changed. 4. Stormwater system in Riverheights is self-contained with sediment traps and French drains. Sediment traps should be inspected and pumped if necessary. 5. Syman and Brighton excavotor contractor will begin to make changes ASAP. 6. A revised ESC site map reflecting changes shall be submitted to PDS.
|
ESC13-00487
| Aging Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 9:56:38 AM | | PASS |
|
|
Finaled.
|
ESC13-00487
| DOC - Permit Finaled | 1/10/2014 | 1/10/2014 | 1/10/2014 9:53:53 AM | P | PASS |
|
|
House complete, landscaped, occupied. BLD permit already finaled. No ESC violations observed.
|
ESC12-00539
| General Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 9:43:42 AM | | PASS |
|
|
No sediment laden snowmelt runoff from open plots observed. BMPs are effective. Stockpiles to East of Old Hickory may be associated with the creek widening project. Will monitor conditions when snow has melted.
|
ESC13-00441
| Aging Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 9:36:56 AM | | PASS |
|
|
Finaled.
|
ESC13-00441
| DOC - Permit Finaled | 1/10/2014 | 1/10/2014 | 1/10/2014 9:32:13 AM | P | PASS |
|
|
House complete and stabilized. No outstanding ESC issues. BLD permit already finaled.
|
ESC13-00222
| Aging Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 9:29:38 AM | | PASS |
|
|
Finaled.
|
ESC13-00222
| DOC - Permit Finaled | 1/10/2014 | 1/10/2014 | 1/10/2014 9:29:19 AM | P | PASS |
|
|
House complete and landscaped. BLD permit finaled, already occupied. No ESC violations.
|
ESC13-01140
| Site Preparation | 1/9/2014 | 1/10/2014 | 1/10/2014 9:02:05 AM | A | PASS |
|
|
Permit is posted. Drop inlets protected. Wattles along alley are installed but may be removed during loading/unloading equipment onto lot. Approved for construction.
|
ESC11-00176
| General Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 8:34:53 AM | | PASS |
|
|
Only 1 or 2 lots left in Solaire #2. The wattle lining the Greenbelt will need to be removed before finaling permit.
|