Inspections for the day of: Thursday, January 11, 1996.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorWes Worcester
TitleBLD-COM/RES INSPECTOR
Phone #340-1490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD95-00567 INSP - Foundation1/11/19961/11/19961/11/1996 12:00:00 AM PART
/ / 342 - special insp on site for walls west of clarifier. log and re
BLD95-00567 INSP - Foundation1/11/19961/11/19961/11/1996 12:00:00 AM PART
/ / 342 - wall west of clarifier
BLD95-00567 INSP - Footings1/11/19961/11/19961/11/1996 12:00:00 AM PART
/ / 342 - poured last 1/4 of clarifier w/special insp on site. log and
BLD95-01233 INSP - Conference1/11/19961/11/19961/11/1996 12:00:00 AM PASS
/ / 342 - ck'd pre-rock and verify 1 hr elevator door requirements w/p
BLD95-01585 INSP - Temporary occupancy1/11/19961/11/19961/11/1996 12:00:00 AM PASS
/ / 342 - adressing handrail return
BLD1053912 INSP - Framing/Rough-in1/11/19961/11/19961/11/1996 12:00:00 AM PASS
/ / 342 - finishing all corrections
BLD95-01675 INSP - Foundation1/11/19961/11/19961/11/1996 12:00:00 AM PART
/ / 342 - special insp on site and will underpin adjacent bldg ftg and
BLD95-02115 INSP - Footings1/11/19961/11/19961/11/1996 12:00:00 AM NR
/ / 342 -
BLD95-01675 INSP - Foundation1/10/19961/11/19961/11/1996 12:00:00 AMANR
01/10/96 342 - REBAR special inspector to be on site
BLD95-01585 INSP - Final1/10/19961/11/19961/11/1996 12:00:00 AMAPART
01/10/96 342 - PORTABLE CLASSROOM
BLD95-00567 INSP - Foundation1/11/19961/11/19961/11/1996 12:00:00 AMPFAIL
01/11/96 342 - ftg, stem wall & slab poured or being poured w/o approval Report pending as well as engineers design and acceptance..2 story CMU blding next to raceway. Notified Joel and Jim Cox. No ftg or brng earth