MEC00-00034
| Final | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | A | PASS |
|
|
call first ###-#### Don. Final ok.
|
MEC99-02945
| Final | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 15:19:35. Contact: ###-####. No access- left notice-called Carol.
|
MEC00-00087
| Final | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 15:31:27. Contact: ###-####. F/P ok.
|
MEC00-00089
| Rough-in | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 15:35:17. Contact: ###-####. Insulate R/H in attic; whole house fan not connected to duct strap up enviro. Exhaust 1/4" sag per foot.
|
MEC00-00039
| Pressure Test | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | A | PASS |
|
|
PER DIXIE PRES TEST. Gas ok.
|
MEC99-02957
| Final | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 09:21:16. Contact: ###-####. Final ok.
|
MEC00-00069
| Final | 1/10/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 10:14:11. Contact: .
|
MEC99-03419
| Final | 1/11/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/11/2000 at 08:03:23. Contact: ###-####. Talked to Ray B. about corrections.
|
MEC00-00096
| Rough-in | 1/11/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | P | FAIL |
|
|
###-####. Not ready.
|
MEC00-00096
| Pressure Test | 1/11/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | P | FAIL |
|
|
Not ready.
|
MEC99-04369
| Pressure Test | 1/11/2000 | 1/11/2000 | 1/11/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/11/2000 at 09:29:57. Contact: ###-####. Gas ok.
|