BLD00-02561
| BLD-Framing/Rough-in | 1/10/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | A | NR |
|
|
John ###-####
|
BLD00-03395
| BLD-Other | 1/10/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | A | PART |
|
|
party wall Mike ###-####
ok to stand fire wall main level 1/11/2001 9:31:08 AM
|
BLD00-03396
| BLD-Other | 1/10/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | A | PART |
|
|
party wall Mike ###-####
ok to stand party wall, nailing ok on main level 1/11/2001 9:31:28 AM
|
BLD00-03225
| BLD-Framing/Rough-in | 1/10/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | A | PASS |
|
|
###-####
ceiling grid ok, verify air diffusers at final 1/11/2001 10:10:15 AM
|
BLD00-02414
| BLD-Framing/Rough-in | 1/9/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 20:13:30. Contact: ###-####.
ok to insulate 1/11/2001 10:43:26 AM
|
BLD00-02411
| BLD-Energy code compliance | 1/9/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 20:14:57. Contact: ###-####.
will call back in 1/11/2001 10:43:05 AM
|
MEC01-00074
| Rough-in | 1/10/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 01/10/2001 at 10:25:38. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 01/11/2001 at 09:54:40.
|
BLD00-02908
| BLD-Final | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 415 On 1/11/2001 9:18:17 AM refinal w/ clean cert. of compliance
c of c # 19903 issued 1/11/2001 11:11:45 AM
|
BLD00-03615
| BLD-Footing | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PART |
|
|
FT INSP ###-#### JEREMY
wip, ok so far 1/11/2001 3:54:38 PM
|
BLD00-03619
| BLD-Footing | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PART |
|
|
JEREMY ###-#### FT
wip, ok so far 1/11/2001 3:54:50 PM
|
BLD00-03620
| BLD-Footing | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PART |
|
|
JEREMY ###-#### FT
wip, ok so far 1/11/2001 3:55:06 PM
|
BLD00-03617
| BLD-Footing | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PART |
|
|
JEREMY ###-#### FT
wip, ok so far 1/11/2001 3:55:21 PM
|
BLD00-03097
| BLD-Framing/Rough-in | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | FAIL |
|
|
FR INSP-RE-INSP -WILL- FOR HOMEOWNER- HOME ###-#### OR WORK AFTER 2 WILL BE ###-#### -PLANS BY NOTICE IN GAR
c/n posted, need eng.// plans redrawn, misc. items 1/11/2001 4:38:08 PM
|
BLD00-02411
| BLD-Energy code compliance | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/11/2001 at 10:15:37. Contact: ###-####.
|
BLD00-02561
| BLD-Framing/Rough-in | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 415 On 1/11/2001 11:19:48 AM rest of shear on front and 1/2 of west
exterior shear ok 1/11/2001 2:33:02 PM
|
BLD00-03321
| BLD-Energy code compliance | 1/11/2001 | 1/11/2001 | 1/11/2001 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 415 On 1/11/2001 3:36:10 PM
mech. had no permit but was only a bath fan and it looked ok, owner said the range would be at a later date and they would get permit at that time for range duct. c/n posted until final insp. 1/11/2001 4:18:33 PM
|