FIR05-00885
| INSP-Final Inspection | 1/10/2006 | 1/11/2006 | 1/11/2006 3:48:07 PM | P | PASS |
|
|
Fire alarm is satisfactory, passed final inspection.
|
BLD05-02558
| FIRE-Final Inspection | 1/11/2006 | 1/11/2006 | 1/11/2006 2:22:16 PM | P | PASS |
|
|
Life safety passed inspection.
|
BLD05-02892
| FIRE-Final Inspection | 1/11/2006 | 1/11/2006 | 1/11/2006 12:16:56 PM | A | PASS |
|
|
Fire life safety finaled, inspection passed.
|
BLD05-02892
| FIRE-Alarm Testing | 1/11/2006 | 1/11/2006 | 1/11/2006 12:14:53 PM | A | PASS |
|
|
Duct smoke detector functioned correctly.
|
BLD05-02030
| FIRE-Final Inspection | 1/11/2006 | 1/11/2006 | 1/11/2006 12:13:31 PM | A | PASS |
|
|
Life safety is satisfactory.
|
BLD05-02030
| FIRE-Alarm Testing | 1/11/2006 | 1/11/2006 | 1/11/2006 12:12:52 PM | A | PASS |
|
|
HVAC duct smoke detector functioned properly.
|
FIR05-00841
| INSP-Sprinkler Rough-in | 1/10/2006 | 1/11/2006 | 1/11/2006 12:07:53 PM | A | PART |
|
|
Overhead rough-in is acceptable to cover pending corrections as noted on plans including overspaced head at kitchen, overspaced head at 2nd floor hall, install head at master bathroom as indicated, the backflow device installed is not as submitted (provide correct device or verify calcs are the same), tenting at cold cavity areas is satisfactory.
|