FIR04-00762
| INSP-Final Inspection | 1/11/2005 | 1/12/2005 | 1/12/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/11/2005 at 9:28:16 AM. Contact: ###-####.
|
FIR04-00582
| INSP-Sprinkler Rough-in/Hydro | 1/11/2005 | 1/12/2005 | 1/12/2005 12:00:00 AM | P | PART |
|
|
Overhead hydro test ok. Plans need to be resubmitted. Both mains are installed closer to the center of the building than shown on the plans and the tail backs are 2" instead of 1". Main out of riser room has also been rerouted. The branchline along the north wall is approx. 7'-2" off of the wall. Plans show 5'-11" 1/12/2005 12:40:29 PM
|
BLD04-01046
| FIRE-Final Inspection | 1/11/2005 | 1/12/2005 | 1/12/2005 12:00:00 AM | P | FAIL |
|
|
Repair emergency light on second floor. Provide fire extinguisher on the second floor. Provide remote annunciators for the duct smoke detectors. Provide approved door hardware for the tenant doors and provide sticker at the main exit. 1/12/2005 4:14:39 PM
|
FIR04-00414
| INSP-Final Inspection | 1/12/2005 | 1/12/2005 | 1/12/2005 12:00:00 AM | P | PASS |
|
|
Fire alarm finaled 1/12/2005 3:09:27 PM
|
FIR04-00783
| INSP-Sprinkler Rough-in/Hydro | 1/12/2005 | 1/12/2005 | 1/12/2005 12:00:00 AM | P | FAIL |
|
|
Pendant in rear classroom is overspaced. 1/12/2005 3:25:59 PM
|
FIR04-00785
| INSP-Final Inspection | 1/12/2005 | 1/12/2005 | 1/12/2005 12:00:00 AM | P | PASS |
|
|
Fire sprinklers finaled 1/12/2005 3:26:25 PM
|