Inspections for the day of: Friday, January 12, 2007.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-02741 FIRE-Final Inspection1/11/20071/12/20071/12/2007 4:04:57 PMPPART
A temporary occupancy was given with dave hannimans permission until the door from the conference room has been installed with approved hardware and the thumbturn is removed from the main exit.
FIR06-00829 INSP-Alarm Testing1/12/20071/12/20071/12/2007 4:02:58 PMPFAIL
Provide as-builts, map at the facp and differential tests for hvac units 4 and 6
FIR07-00021 INSP-Final Inspection1/12/20071/12/20071/12/2007 2:23:22 PMPFAIL
I could not verify hangers above the newly installed hardlid ceilings.
FIR06-00900 INSP-Final Inspection1/12/20071/12/20071/12/2007 2:11:35 PMPPASS
permit finaled
FIR06-00968 INSP-Final Inspection1/12/20071/12/20071/12/2007 2:11:14 PMPPASS
permit finaled
FIR06-00733 INSP-Final Inspection1/12/20071/12/20071/12/2007 1:42:18 PMPPASS
Permit finaled
FIR06-00603 INSP-Final Inspection1/12/20071/12/20071/12/2007 1:39:38 PMPPASS
Permit finaled
FIR06-00631 INSP-Sprinkler Rough-in/Hydro1/11/20071/12/20071/12/2007 1:39:09 PMAPASS
overhead hydro and roughin passed.
FIR05-00644 INSP-Sprinkler Rough-in/Hydro1/11/20071/12/20071/12/2007 10:43:29 AMAPASS
hydro test for the 1st, 2nd, 3rd and 4th floors has passed.
FIR06-00623 INSP-Sprinkler Rough-in/Hydro1/11/20071/12/20071/12/2007 9:42:58 AMAPASS
Overhead hydro test passed.