FIR09-00575
| INSP-Sprinkler Rough-in | 1/12/2010 | 1/12/2010 | 1/12/2010 4:05:59 PM | P | PASS |
|
|
The remaining sprinkler piping for the first and second floor elevator lobbys are ok to cover.
|
BLD09-00945
| FIRE-Conference | 1/11/2010 | 1/12/2010 | 1/12/2010 3:46:07 PM | A | DONE |
|
|
I went over life safety requirements for the remodel in the existing main lobby area. I found that fire alarm modifications that were not previously shown on the project related fire alarm permit will need to be submitted to show the changes that are required due to the use change in this lobby area.
|
FIR09-00484
| INSP-Sprinkler Rough-in/Hydro | 1/11/2010 | 1/12/2010 | 1/12/2010 3:34:52 PM | A | PASS |
|
|
The overhead hydro test passed.
|
BLD06-00535
| FIRE-Final Inspection | 1/12/2010 | 1/12/2010 | 1/12/2010 11:56:35 AM | A | PASS |
|
|
Life safety passed.
|
BLD09-02298
| FIRE-Final Inspection | 1/11/2010 | 1/12/2010 | 1/11/2010 3:27:47 PM | A | PASS |
|
|
Life safety passed. Single action hardware to be provided on the restroom door prior to the building inspection.
|