ESC13-01323
| Site Final | 1/5/2016 | 1/12/2016 | 1/12/2016 3:57:31 PM | P | FAIL |
|
|
No site final clean up or removal of temp BMPs. Multiple requests issued to Andersen Construction.
Minor construction/landscaping around clubhouse is near completion.
|
ESC15-00351
| Aging Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 3:45:37 PM | | PASS |
|
|
WIP. Permit signs posted. No significant trackout. No muddy runoff.
|
ESC15-00352
| Aging Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 3:45:26 PM | | PASS |
|
|
WIP. Permit signs posted. No significant trackout. No muddy runoff.
|
ESC15-01483
| General Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 3:27:25 PM | P | PASS |
|
|
WIP on site demolition activities. No trackout or discharges observed.
DI bags installed at both 10th and 11th at Bannock as requested.
Perimeter BMPs to be installed as demo of sidewalk and landscape curbing is completed. Will continue to monitor.
|
ESC14-00299
| General Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 2:47:48 PM | | PEND |
|
|
|
ESC14-00921
| Random Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 2:46:15 PM | P | PASS |
|
|
No sediment or discharges from site. WiP . ESC permit sign posted. No access to site from Warm Springs, access through alley. No significant trackout. No corrections.
|
ESC15-00858
| General Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 2:41:54 PM | P | PASS |
|
|
WIP. Locust and Franklin Street are clean. Storm drain on corner has sediment mat installed. No violations observed. Approved
|
ESC15-01004
| Tracking Control | 1/12/2016 | 1/12/2016 | 1/12/2016 2:24:00 PM | P | PASS |
|
|
rock entrance maintenance inspection
Trackout observed yesterday was cleaned. Currently operating on top of tracking pad and no significant trackout. Will check back tomorrow
Note - DI bag installed on 6th and Myrtle as requested during site prep.
|
ESC15-00789
| Tracking Control | 1/12/2016 | 1/12/2016 | 1/12/2016 2:09:25 PM | P | PART |
|
|
check to see if rock entrance needs maintenance
Rock entrance installed but needs to be turned over and more rock installed. Some trackout to 9th street has been observed to 9th yesterday and today.
Correction request to improve entrance to prepare for forecasted precipitation.
RP Jason with Andersen stated excavator is bringing more rock tomorrow AM. Will check back later in week.
All other BMPs in good condition,
|
ESC15-01347
| BMP Violation | 1/12/2016 | 1/12/2016 | 1/12/2016 12:24:55 PM | P | FAIL |
|
|
Multiple BMP violations at site observed as well at ESC15-01349. Onsite inspection with RP Austin.
- no site prep inspection requested - no yellow permit sign posted at time of inspection - streets and sidewalk dirty with trackout without regular sweeping or housekeeping - trash and construction wrappings accumulated along Wildwood.
Corrections issued: - street, gutter, and sidewalk sweeping - change out inlet bag on alley - post yellow permit sign - provide designated concrete washout pit
Re- inspection and fee required. Written Correction Notice given to RP Austin. $55 re-inspection fee assessed to site. No parcel hold currently.
|
ESC15-01576
| Site Preparation | 1/11/2016 | 1/12/2016 | 1/12/2016 11:49:41 AM | A | PASS |
|
|
Matt Phone #: ###-####
Permit sign posted. Storm drain for new culdesac has inlet bag installed with adequate capacity.
Lot has earthen berm around perimeter that is to be preserved in leiu of a silt fence along the north border. Adajacent property has a pond which has vegetative buffer that also must be undisturbed. Check next inspection.
RP to install construction fencing to keep workers from accessing lot from Skycrest Street.
Approved for construction.
|
ESC15-01349
| General Inspection | 1/8/2016 | 1/12/2016 | 1/12/2016 10:50:10 AM | A | FAIL |
|
|
Biltmore projects on Race out of compliance:
- DI bags need maintenance - pick up windblown trash and litter - roads and gutters are very dirty, street sweeping and manual sweeping is required.
Onsite meeting called for 12 today.
|
ESC11-00192
| General Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 9:43:00 AM | | PASS |
|
|
|
ESC14-01139
| General Inspection | 1/12/2016 | 1/12/2016 | 1/12/2016 9:11:36 AM | | PASS |
|
|
Storage structure within confined storage yard is complete with no excavation or disturbed areas. Low risk industrial site. No further ESC inspections necessary.
|
ESC14-01139
| DOC - Permit Finaled | 1/12/2016 | 1/12/2016 | 1/12/2016 9:09:32 AM | P | PASS |
|
|
|