Inspections for the day of: Thursday, January 12, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-01291 FIRE-Conference1/12/20171/12/20171/12/2017 2:50:38 PMPDONE
I spoke to the general contractor about getting the fire hydrant located along Eagle Rd rotated as per the approved drawings. He was going to follow up with Suez.
FIR16-00722 INSP-Sprinkler Rough-in1/12/20171/12/20171/12/2017 2:49:35 PMPCANC
Colton Cox is the contact for this inspection. He is requesting and inspection in Building #1 and #2. His number is ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR16-00704 INSP-Sprinkler Rough-in/Hydro1/11/20171/12/20171/12/2017 1:58:16 PMPPART
Rough-in Inspection passed with the seismic brace added. Started the 24hr Air test at 2:00pm with 50 psi on the guage.
BLD13-02296 FIRE-Final Inspection1/11/20171/12/20171/12/2017 12:30:34 PMPPASS
Life safety passed
FIR16-00721 INSP-Sprinkler Rough-in1/12/20171/12/20171/12/2017 12:30:09 PMPPASS
Rough-in passed. The tenting only partialy passed. Piping can be covered in the interior of the building but the piping in the exterior storage rooms and the riser room can not be covered.
FIR16-00792 INSP-Final Inspection1/11/20171/12/20171/12/2017 8:31:02 AMAPASS
Permit finaled