BLD16-01291
| FIRE-Conference | 1/12/2017 | 1/12/2017 | 1/12/2017 2:50:38 PM | P | DONE |
|
|
I spoke to the general contractor about getting the fire hydrant located along Eagle Rd rotated as per the approved drawings. He was going to follow up with Suez.
|
FIR16-00722
| INSP-Sprinkler Rough-in | 1/12/2017 | 1/12/2017 | 1/12/2017 2:49:35 PM | P | CANC |
|
|
Colton Cox is the contact for this inspection. He is requesting and inspection in Building #1 and #2. His number is ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR16-00704
| INSP-Sprinkler Rough-in/Hydro | 1/11/2017 | 1/12/2017 | 1/12/2017 1:58:16 PM | P | PART |
|
|
Rough-in Inspection passed with the seismic brace added. Started the 24hr Air test at 2:00pm with 50 psi on the guage.
|
BLD13-02296
| FIRE-Final Inspection | 1/11/2017 | 1/12/2017 | 1/12/2017 12:30:34 PM | P | PASS |
|
|
Life safety passed
|
FIR16-00721
| INSP-Sprinkler Rough-in | 1/12/2017 | 1/12/2017 | 1/12/2017 12:30:09 PM | P | PASS |
|
|
Rough-in passed. The tenting only partialy passed. Piping can be covered in the interior of the building but the piping in the exterior storage rooms and the riser room can not be covered.
|
FIR16-00792
| INSP-Final Inspection | 1/11/2017 | 1/12/2017 | 1/12/2017 8:31:02 AM | A | PASS |
|
|
Permit finaled
|