Inspections for the day of: Thursday, January 13, 2000.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-01516 BLD-Final1/12/20001/13/20001/14/2000 12:00:00 AMAPASS
l/c isuedScheduled by a contractor via Hello! on 01/12/2000 at 08:25:36. Contact: ###-####.
BLD99-02027 BLD-Framing/Rough-in1/13/20001/13/20001/14/2000 12:00:00 AMPCANC
sheer Ken Jensen ###-####
BLD99-01212 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMAPASS
###-####. L/C issued.
BLD99-01213 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMAPASS
###-####. L/C issued.
BLD99-01214 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMAPASS
L/C issued.
BLD99-02822 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 01/12/2000 at 13:17:20. Contact: ###-####. Type II hood only! Shaft that was const. hood was modified & will not meet the hood requirements for type I. 1/18/00 1:15:15 PM
BLD98-00550 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMACANC
###-#### WARD
BLD99-02344 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMPFAIL
###-#### CURT
BLD99-01752 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMPPASS
###-####
BLD99-03247 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMPFAIL
Return air from dock must be protected.
BLD99-01106 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMPPASS
###-#### Jeff L/C
BLD99-01107 BLD-Final1/12/20001/13/20001/13/2000 12:00:00 AMPPASS
L/C
BLD99-02572 BLD-Concrete1/13/20001/13/20001/13/2000 12:00:00 AMPPART
grouting at 2pm john ###-#### Topout & grout lift on e8,e7,e6&e1 ok to first floor elevation. Rebar & form repair pier engineering
BLD99-02780 BLD-Framing/Rough-in1/13/20001/13/20001/13/2000 12:00:00 AMPPASS
###-#### Egress windows and window wells ok
BLD99-02049 BLD-Concrete1/13/20001/13/20001/13/2000 12:00:00 AMPFAIL
###-#### TOM\\COL B C D E F ALL IN LINE ONE SECOND DECK, Col. ok pending SI report work in progress/c/n issued for col link 2 39 inch e/u for gaurdrail cabbles will not meet 42 inch min submit change.
BLD99-03446 BLD-Framing/Rough-in1/13/20001/13/20001/12/2000 12:00:00 AMPNR
Scheduled by a contractor via Hello! on 01/13/2000 at 08:22:47. Contact: ###-####. fireblock not done and insulation work in progress.