BLD04-02323
| BLD-Energy code compliance | 1/12/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | A | PASS |
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD04-02040
| BLD-Framing/Rough-in | 1/12/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | A | PASS |
|
|
Jay; Phone #: ###-#### Internet Inspection Request from: Jan Rice c/n items completed still ok to insulate 1/13/2005 9:17:03 AM
|
BLD04-01845
| BLD-Final | 1/12/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 1/12/2005 at 1:44:52 PM. Contact: ###-####.
|
BLD04-02446
| BLD-Energy code compliance | 1/12/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 1/12/2005 at 1:46:21 PM. Contact: ###-####.
|
BLD03-02187
| BLD-Conference | 1/13/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | A | PART |
|
|
fire dampers in 2hr wall not installed per manfactors rec crew will rework 1/13/2005 10:01:22 AM
|
BLD04-01435
| BLD-Final | 1/13/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | P | PASS |
|
|
John-call before you go; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD04-01952
| BLD-Final | 1/12/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | P | CANC |
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie - called rescheduling rob 1/13/2005 9:46
|
BLD04-02885
| BLD-Conference | 1/13/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 1/13/2005 at 8:11:53 AM. Contact: ###-####.
|
BLD04-01323
| BLD-Foundation | 1/13/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | P | PART |
|
|
Grout placement at 1:30 pm Internet Inspection Request from: Alex Monge
|
BLD03-01692
| BLD-Framing/Rough-in | 1/13/2005 | 1/13/2005 | 1/13/2005 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 1/13/2005 at 8:29:18 AM. Contact: ###-####. ceiling grid ok 1/14/2005 8:07:47 AM
|