FIR09-00536
| INSP-Conference | 1/14/2010 | 1/14/2010 | 1/14/2010 4:34:03 PM | P | DONE |
|
|
|
FIR08-00321
| INSP-Final Inspection | 1/13/2010 | 1/14/2010 | 1/14/2010 4:32:18 PM | P | PASS |
|
|
Fire alarm work completed satisfactory, C/N items finished, permit finaled.
|
FIR09-00492
| INSP-Final Inspection | 1/11/2010 | 1/14/2010 | 1/14/2010 4:31:13 PM | P | PASS |
|
|
Hood suppression system operated correctly under test conditions, inspection passed, permit finaled.
|
FIR09-00736
| INSP-Final Inspection | 1/14/2010 | 1/14/2010 | 1/14/2010 4:29:47 PM | A | PASS |
|
|
Corrections verified for completion, fire sprinkler permit finaled.
|
BLD09-01838
| FIRE-Conference | 1/14/2010 | 1/14/2010 | 1/14/2010 4:28:27 PM | A | DONE |
|
|
Regarding project related fire alarm permit work.
|
FIR09-00612
| INSP-Sprinkler Rough-in | 1/13/2010 | 1/14/2010 | 1/14/2010 4:27:40 PM | A | PART |
|
|
Overhead rough-in is satisfactory except as noted on plans-one area missing drops is incomplete, main level bedroom #2 head appears too close to a ceiling fan as marked on drawings, riser not yet tied in, discussed supply line flush, tenting is acceptable.
|