FIR10-00521
| FIR-Aging Inspection | 1/14/2013 | 1/14/2013 | 1/15/2013 3:08:01 PM | | NR |
|
|
|
FIR12-00557
| INSP-Final Inspection | 1/14/2013 | 1/14/2013 | 1/14/2013 3:58:50 PM | P | FAIL |
|
|
For todays inspection we verified strobe spacing in the high ceiling areas. At the east end of the building Rand and I agreed that relocating one strobe in the low ceiling area will provide coverage in another high ceiling area. That work was performed as I waited. The smoke detectors were tested as well. However no signals were received at the monitoring station. To final this project signals need to be received, as-builts provided, map at the facp.
|
FIR12-00728
| INSP-Final Inspection | 1/11/2013 | 1/14/2013 | 1/14/2013 1:44:42 PM | A | PASS |
|
|
Permit finaled
|
FIR12-00637
| INSP-Supply line flush | 1/11/2013 | 1/14/2013 | 1/14/2013 1:08:19 PM | A | PASS |
|
|
Underground flush passed.
|
BLD10-02541
| FIRE-Final Inspection | 1/11/2013 | 1/14/2013 | 1/14/2013 10:06:43 AM | A | PASS |
|
|
Life safety passed
|