Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00736 BLD-Framing/Rough-in1/14/20021/15/20021/15/2002 12:00:00 AMAPART
###-####. Went out to review area separation walls, as architect would like to revise configuration of wall at the area of mechanical chases for restroom exhaust duct. Needs suppervisor approval possible plan check modification . 1/15/2002 4:46:31 PM
BLD01-00308 BLD-Final1/14/20021/15/20021/15/2002 12:00:00 AMAPART
###-#### Went over items again was trying to have suppervisor here this day , but could not. 1/15/2002 5:06:16 PM
BLD01-01956 BLD-Framing/Rough-in1/14/20021/15/20021/15/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 01/14/2002 at 18:31:27. Contact: ###-####. I have approved the revised floor plan and have a letter owner 1/15/2002 4:38:19 PM 1/15/2002 4:39:16 PM a 1/15/2002 4:39:16 PM to employ no more than 4 people. 1/15/2002 4:39:48 PM
BLD01-00621 BLD-Framing/Rough-in1/15/20021/15/20021/15/2002 12:00:00 AMPPART
ceiling\\###-#### mike. west area ok east still in process. Also recieved ok from Architect fr cell walls not to deck and ok for column fire proffing in place of sheetrocked protection,still waiting for 2 hour occupancy wll change at the rear area of restrooms, also still need to caulk mis penetrations through out at exit corid and 2 hr oc wall around holding cell.s 1/17/2002 1:16:38 PM
BLD01-00122 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
dirk ###-#### fnneeds to post a bond. 1/22/2002 11:24:44 AM
BLD01-00123 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
dirk ###-####--fn Need bond posted before a temp oc 1/22/2002 11:01:26 AM
BLD01-00121 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
fn dirk ###-####
BLD01-00120 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
fn dirk ###-####-
BLD01-00118 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
fn dirk ###-####
BLD01-00117 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
fn dirk ###-####
BLD01-00116 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
fn dirk ###-####
BLD01-00115 BLD-Final1/15/20021/15/20021/15/2002 12:00:00 AMPNR
fn dirk ###-####
BLD01-02254 BLD-Framing/Rough-in1/16/20021/15/20021/15/2002 12:00:00 AMPFAIL
Scheduled by Inspector: 407 On 1/16/2002 3:37:49 PM grid ceiling. 1/17/2002 1:17:04 PM