BLD01-02260
| BLD-Final | 1/14/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 01/14/2002 at 12:45:27. Contact: ###-####.
|
BLD01-02943
| BLD-Final | 1/14/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | A | PASS |
|
|
###-####
|
BLD01-03243
| BLD-Foundation | 1/14/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 01/14/2002 at 18:01:47. Contact: ###-####.
|
BLD01-02793
| BLD-Framing/Rough-in | 1/14/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | A | NR |
|
|
###-#### rough ins not completed 1/15/2002 10:33:54 AM
|
BLD01-00460
| BLD-Framing/Rough-in | 1/14/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 01/14/2002 at 12:14:07. Contact: ###-####. wip ok to cover bath walls and ceiling 1/15/2002 10:17:39 AM
|
BLD01-02494
| BLD-Foundation | 1/14/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 01/14/2002 at 12:22:45. Contact: ###-####. wip 1/15/2002 2:57:02 PM
|
BLD00-02288
| BLD-Wall cover | 1/11/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/11/2002 at 09:29:53. Contact: ###-####. drop ceilings for cover east 4 units of bld 14 1/15/2002 10:42:13 AM
|
MEC02-00138
| Rough-in | 1/15/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | P | PASS |
|
|
###-#### DUANE
|
MEC02-00138
| Pressure Test | 1/15/2002 | 1/15/2002 | 1/15/2002 12:00:00 AM | P | PASS |
|
|
###-#### DUANE done by intermountain 1/15/2002 2:49:49 PM
|