ELE08-01732
| ELE-Aging Inspection | 1/15/2009 | 1/15/2009 | 1/16/2009 2:04:24 PM | | DONE |
|
|
called, suc
|
ELE09-00074
| Final | 1/15/2009 | 1/15/2009 | 1/15/2009 3:58:30 PM | P | CANC |
|
|
Temporary 240V outlet fixed. Thank You! Darryn Phone #: ###-#### Internet Inspection Request from: Darryn Coburn wrong type request, see t/s, no esc this project
|
ELE09-00074
| Temporary Service | 1/15/2009 | 1/15/2009 | 1/15/2009 3:58:03 PM | P | PASS |
|
|
Temporary 240V outlet fixed. Thank You! Darryn Phone #: ###-#### Internet Inspection Request from: Darryn Coburn corrections made, t/s u/g n ok, no esc this project
|
ESC08-00152
| General Inspection | 1/15/2009 | 1/15/2009 | 1/15/2009 3:26:34 PM | P | PASS |
|
|
looked ok
|
ESC06-01299
| General Inspection | 1/15/2009 | 1/15/2009 | 1/15/2009 2:56:02 PM | P | PASS |
|
|
looked ok
|
ELE07-03307
| Electrical Rough-In | 1/14/2009 | 1/15/2009 | 1/15/2009 2:22:35 PM | P | PASS |
|
|
Contact: Neil Ramsey. Rough-in inspection of: Elevator Fronts floors 14-18; Elevator Fronts basement & 1st floor; Elevator Lobby rough-in walls. Early afternoon if at all possible. Phone #: ###-#### Internet Inspection Request from: Shelli Daylong elevator fronts - basement, 1, 14,15,16,17,18, 1st floor lobby only ok to cover
|
ELE08-03224
| Electrical Rough-In | 1/14/2009 | 1/15/2009 | 1/15/2009 1:33:22 PM | P | PASS |
|
|
Floor heat in sun room by kitchen Phone #: ###-#### Internet Inspection Request from: Jim Williams ok to cover floor heat only, no esc this project
|
ELE09-00075
| Permanent Service | 1/15/2009 | 1/15/2009 | 1/15/2009 12:26:45 PM | P | NR |
|
|
Robert Phone #: ###-#### called owner, he is procuring cord for trailer, will call when installed
|
ELE08-02901
| Final | 1/14/2009 | 1/15/2009 | 1/15/2009 10:37:52 AM | A | PART |
|
|
MORGAN Phone #: ###-#### Internet Inspection Request from: Sean DeLacy ok to final 3rd floor only, did not sign card, core and shall shall be done, then can sign occupancy card, no esc this project
|
ELE08-02464
| Permanent Service | 1/14/2009 | 1/15/2009 | 1/15/2009 9:25:09 AM | A | CANC |
|
|
joe Phone #: ###-#### wrong type request, see conference, no esc this project
|
ELE08-02464
| Conference | 1/15/2009 | 1/15/2009 | 1/15/2009 9:24:43 AM | A | DONE |
|
|
joe Phone #: ###-#### talked to owner, told to pull conductor into meter lug so that insulation not damaged, drive in ground rods, use plastic bushing for ground wire abrasion protection, add bond bushing for nipple into panel, add conduit strap for riser, no esc this project
|
ELE09-00070
| Electrical Rough-In | 1/14/2009 | 1/15/2009 | 1/15/2009 8:54:35 AM | A | PASS |
|
|
Jay Phone #: ###-#### ric basement ok, no esc this project
|
ELE08-01862
| Final | 1/14/2009 | 1/15/2009 | 1/15/2009 8:10:58 AM | A | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Jim Williams ok to final, signed occupancy card
|