BLD06-01451
| FIRE-Conference | 1/15/2009 | 1/15/2009 | 1/16/2009 11:18:08 AM | A | DONE |
|
|
Regarding fire code review notes on areas of refuge.
|
BLD06-01451
| FIRE-Conference | 1/15/2009 | 1/15/2009 | 1/15/2009 4:31:45 PM | P | DONE |
|
|
Duplicate request
|
FIR08-00816
| INSP-Sprinkler Rough-in | 1/15/2009 | 1/15/2009 | 1/15/2009 4:25:45 PM | P | PART |
|
|
Need to provide stamped plan set on site for review, preliminary rough-in inspection okay with the exception of one missing ret. strap, one EQ brace not yet installed, also noted one damaged pendent head to be removed, existing heads at the north side are still in service, 2 1/2" main tie in is incomplete. Discussed hydro test schedule.
|
FIR08-00369
| INSP-Sprinkler Rough-in | 1/15/2009 | 1/15/2009 | 1/15/2009 4:20:27 PM | P | PART |
|
|
Correction notice items per last inspection are finished, verified resubmitted plans for field changes, rough-in passed.
|
FIR08-00669
| INSP-Final Inspection | 1/15/2009 | 1/15/2009 | 1/15/2009 4:18:36 PM | P | FAIL |
|
|
See comment notes 1/15 for correction items.
|
BLD08-02450
| FIRE-Final Inspection | 1/15/2009 | 1/15/2009 | 1/15/2009 4:17:32 PM | P | PART |
|
|
Racks as installed at the east side passed inspection, remainder of racking per permit scope is not yet constructed- see plans for areas inspected today.
|
FIR08-00369
| INSP-Sprinkler Rough-in/Hydro | 1/14/2009 | 1/15/2009 | 1/15/2009 1:20:45 PM | A | PART |
|
|
OH hydrostatic testing completed satisfactory.
|
BLD08-01034
| FIRE-Final Inspection | 1/14/2009 | 1/15/2009 | 1/15/2009 1:18:49 PM | A | FAIL |
|
|
chad Phone #: ###-#### See comments for project related fire alarm permit.
|
FIR08-00669
| INSP-Final Inspection | 1/13/2009 | 1/15/2009 | 1/15/2009 1:17:12 PM | A | FAIL |
|
|
Noted locations of adjustments to be made including cd settings, overspacing, obstructed devices, lacking coverage, etc.
|
FIR08-00766
| INSP-Sprinkler Rough-in | 1/14/2009 | 1/15/2009 | 1/15/2009 1:14:28 PM | A | PART |
|
|
See annotations initialed with today's date for location of two stubs and riser pieces okayed for cover at the south/central side of the building.
|
FIR08-00369
| INSP-Final Inspection | 1/14/2009 | 1/15/2009 | 1/14/2009 11:25:59 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 1/14/2009 at 11:08:00 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jan 14 2009 11:25AM.
|