Inspections for the day of: Thursday, January 15, 2009.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC08-00968 Tracking Control1/15/20091/15/20091/15/2009 4:00:22 PMPFAIL
24hr verbal correction to RP:
1.Clean up all tracking from alley way due to construction traffic. Also contact ACHD on the muddy alley way
2. Clean all sediment and debris off of the street area.
Will re-inspect on 1/16/09 PM
ESC08-00575 General Inspection ESC1/15/20091/15/20091/15/2009 3:25:08 PM FAIL
Left a message for the RP at the number given.
Clean up all sediment and debris off of all hard surfaces trough out the whole subdivision. Will re-inpsect on 1/21/09
ESC08-00821 General Inspection1/15/20091/15/20091/15/2009 3:01:13 PMPPASS
ESC08-01023 Site Preparation ESC1/15/20091/15/20091/15/2009 11:23:23 AM FAIL
Verbal to RP:
1. Post the correct ESC sing at the entrance of project area.
2. Stabilize or block off the access point at the west end.
Will re-inspect on 1/21/09.
ESC07-01595 Tracking Control1/12/20091/15/20091/15/2009 10:24:21 AMAPASS
All issues dealt with from the prior inspection.
ESC08-00725 BMP Violation1/12/20091/15/20091/15/2009 10:19:32 AMAPART
Verbal to RP:
the way that the wattle is staked inplace, you use a twine to keep it sitting down into the trach. Or re-stake it through the center of the wattle. Also clean up all sediment off of the hard surfaces on a daily basis. Will re-inspect on 1/21/09AM.
ESC08-01017 Site Preparation1/15/20091/15/20091/15/2009 9:59:52 AM PART
Left message with RP:
Concrete washout not provided at this time. Must provide a washout pit (external or pit) prior to concrete pour. Will re-inspect on 1/20/09.