Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-01283 General Inspection1/15/20161/15/20161/19/2016 3:35:27 PMPPEND
No violations at site. Limited activity. Foundation has been poured. Assessed fees for previous violations have not yet been paid.
ESC15-00107 DOC - Permit Finaled1/15/20161/15/20161/15/2016 3:55:55 PMPPASS
Historic home is removed and site now cleared for new project (The Roost/Fowler), see ESC15-00762. ESC permit conditions met.
ESC15-00104 DOC - Permit Finaled1/15/20161/15/20161/15/2016 3:55:33 PMPPASS
Historic home is removed and site now cleared for new project (The Roost/Fowler), see ESC15-00762. ESC permit conditions met.
ESC15-00103 DOC - Permit Finaled1/15/20161/15/20161/15/2016 3:55:12 PMPPASS
Historic home is removed and site now cleared for new project (The Roost/Fowler), see ESC15-00762. ESC permit conditions met.
ESC15-00762 Site Preparation1/14/20161/15/20161/15/2016 3:44:01 PMAPEND
Spoke with RP for project. Onsite ESC/SWPPP meeting will be scheduled for next week.
ESC14-00983 General Inspection1/15/20161/15/20161/15/2016 3:04:56 PM PART
No activity. No permit sign.

Need to post sign and install BMPs to prepare for further construction (construction entrance)
ESC15-00623 General Inspection1/15/20161/15/20161/15/2016 2:59:12 PM CANC
rescheduled
ESC14-01040 General Inspection1/15/20161/15/20161/15/2016 2:47:33 PM PART
Construction complete at Breckenwood and open areas have been stabilized. No trackout or discharges.

Need to remove sediment bag on Shelly MS4 and remove DI bags within complex or have owners agree to maintain them.
ESC15-00504 Random Inspection1/15/20161/15/20161/15/2016 2:45:26 PMPPASS
Streets recentlly swept, no trackout or dischareges observed at Kensington. DI bags installed on Saxton and Gary Lane.
ESC15-00935 Aging Inspection1/15/20161/15/20161/15/2016 2:32:20 PM PASS
Home complete and occupied. Homeowner to complete landscaping. No sediment leaving site, and dirt is graded below curb levels.Active construction on Steve Ct. in progress. ESC permit finaled.
ESC15-00935 DOC - Permit Finaled1/15/20161/15/20161/15/2016 2:31:04 PMPPASS
ESC14-01052 General Inspection1/15/20161/15/20161/15/2016 2:07:39 PM PART
No trackout or discharges to Maple Grove or to the MS4. Several units at the front of Ashville Commons are complete and sod has been laid. Several apartments are occupied.

SWPPP sign and box are still posted, though there are no recent site inspections, possibly due to vertical construction only?

Lots of trash, boxes, building materials along South Slough. Even some ventilation tubing in ditch itself. Shows lack of housekeeping and inadequate waste management.

At the east end of parking/access area there is a lot of mud and other debris. The permeable pavement has mud and sediment all over it which will prevent proper drainaige.

Corrections to pick up trash and protect/clean newly installed stormwater infrastructure to Biltmore RP.
ESC15-01347 BMP Violation1/12/20161/15/20161/15/2016 1:28:46 PMACANC
Follow up on CN issued Tuesday 1/12

Compliance date extended due to recent snow/rainfall received
ESC14-00059 DOC - Permit Finaled1/15/20161/15/20161/15/2016 12:36:48 PMPPASS
ESC14-00059 General Inspection1/15/20161/15/20161/15/2016 12:36:21 PM FAIL
Need to change out DI bag that is receiving dirty sheet flow from the new phase of Cordillera. Need to sweep parking lots when conditions dry.

No active construction in this phase, no further inspections on this permit. See ESC15-00336 for active corrections. Same RP. This permit finaled.
ESC15-01091 BMP Violation1/13/20161/15/20161/15/2016 9:35:31 AMPPEND
RP acknowledged correction requests issued and has started clean up process. Overnight snowfalls have delayed some operations since Wednesday. Will re-inspect early next week to check conditions after the foundation has been backfilled. Wattles will be reinstalled.
ESC15-00643 General Inspection1/15/20161/15/20161/15/2016 9:10:27 AM PASS
Project complete. ESC conditions satisfied.
ESC15-00643 DOC - Permit Finaled1/15/20161/15/20161/15/2016 9:10:12 AMPPASS