BLD97-01116
| INSP - Final | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | A | PASS |
|
|
CARD TO CATHY; LC ONLY
|
BLD97-03736
| INSP - Conference | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | A | PASS |
|
|
W/ TABBY JOLLY RE CHURCH PROJECT OF SLY'S; CALLED SLY, NO SPEC INSP REQ'D...< 2500PSI Fc concrete. HE CAN DO IT.
|
MEC98-00152
| INSP - Final | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | PASS |
|
|
PRESSURE TEST ONLY--PROBLEM CALL JIM AT ###-####....MINOR ADD'N TO RUN TO NEW STOVE.
|
MEC98-00152
| INSP - Final | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | PASS |
|
|
PRESSURE TEST ONLY--PROBLEM CALL JIM AT ###-####....MINOR ADD'N TO RUN TO NEW STOVE.
|
BLD96-02800
| INSP - Conference | 1/20/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | PASS |
|
|
W/ SUPT. RE: RESPONSE TO C/N'S FOR FIRESTOPS & "TESTED ASSY" OF RATED WALLS; WILL NEED TO MEET W/ ARCH.
|
BLD97-01571
| INSP - Foundation | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | NR |
|
|
DOCKSIDER; poured w/o insp...no plan or responsible party onsite, told bartender to have owner call me.
|
BLD97-01772
| INSP - Carpentry | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | PART |
|
|
CHK PROGRESS
|
BLD97-02259
| INSP - Framing/Rough-in | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | PART |
|
|
GOOD SAMARITAN JOEL BROWN ###-####\PARTIAL...CALLED JOEL, COULDN'T FIND ONSITE, NO RESPONSE. WORK AT ROOMSIDE OF AREA B LOOKED OK, LEFT NOTE
|
BLD97-02537
| INSP - Final | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | NR |
|
|
CALL LAVORIA AT OFFICE ####-#### AND SHE WILL MEET YOU...CALLED OWNER & JESSE AT REHAB, NO OTHER INSPS SHOWN. PLBG, ELEC PERMITS??? WILL RESCHED.
|
BLD97-03651
| INSP - Conference | 1/16/1998 | 1/16/1998 | 1/16/1998 12:00:00 AM | P | PASS |
|
|
W/ CONC. CONTRACTOR....INSP REQ'S...NEED ENG'S LETTER.
|