Inspections for the day of: Friday, January 16, 2004.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM04-00071 Plumbing Rough-in1/15/20041/16/20041/16/2004 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 1/15/2004 at 4:27:48 PM. Contact: ###-####.
PLM04-00098 Water and/or Sewer1/15/20041/16/20041/16/2004 12:00:00 AMAPASS
###-#### jerry
PLM04-00100 Water and/or Sewer1/15/20041/16/20041/16/2004 12:00:00 AMAPASS
###-#### LARRY
PLM02-00943 Final1/16/20041/16/20041/16/2004 12:00:00 AMAPASS
PLM03-00105 Final1/16/20041/16/20041/16/2004 12:00:00 AMPPASS
###-#### DEAN
PLM03-02998 Plumbing Rough-in1/15/20041/16/20041/16/2004 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 1/15/2004 at 2:51:14 PM. Contact: ###-####. rough-in for area b class room,s test ok 1/16/2004 2:16:28 PM
PLM04-00078 Water and/or Sewer1/16/20041/16/20041/16/2004 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 1/16/2004 at 7:35:11 AM. Contact: ###-####.
PLM04-00079 Water and/or Sewer1/16/20041/16/20041/16/2004 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 1/16/2004 at 7:36:58 AM. Contact: ###-####.
PLM03-03861 Final1/16/20041/16/20041/16/2004 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 1/16/2004 at 8:01:51 AM. Contact: ###-####.