Inspections for the day of: Wednesday, January 16, 2008.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00011 INSP-Alarm Testing1/16/20081/16/20081/18/2008 12:08:58 PMPDONE
The interconnections between the central tower and the north tower on 2nd, 3rd, 4th and 5th floors passed.
BLD07-02807 FIRE-Final Inspection1/16/20081/16/20081/16/2008 5:11:11 PMPPASS
Sprinkler permit completed. Life safety passed. KR
FIR07-01024 INSP-Final Inspection1/15/20081/16/20081/16/2008 5:08:08 PMAPASS
ceiling tiles installed.Work completed. KR
BLD06-01940 FIRE-Final Inspection1/14/20081/16/20081/16/2008 9:55:02 AMAPASS
life safety passed.
BLD07-02602 FIRE-Final Inspection1/15/20081/16/20081/16/2008 8:57:58 AMAPASS
fire life safety passed
BLD08-00015 FIRE-Final Inspection1/14/20081/16/20081/16/2008 8:53:25 AMAPASS
life safety passed
FIR07-00637 INSP-Final Inspection1/15/20081/16/20081/16/2008 8:38:48 AMAPASS
Permit finaled
FIR07-00941 INSP-Final Inspection1/15/20081/16/20081/16/2008 8:16:38 AMAPASS
permit finaled
BLD07-02807 FIRE-Final Inspection1/15/20081/16/20081/16/2008 12:00:00 AMACANC
roberto - fire life safety Phone #: ###-####