BLD14-03664
| FIRE-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 5:26:04 PM | P | PASS |
|
|
Verified previous correction notice items. Fire life safety finaled.
|
BLD12-02886
| FIRE-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 4:23:07 PM | P | PASS |
|
|
C/N items completed. Fire life safety finaled.
|
FIR14-00261
| INSP-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 4:21:27 PM | P | PASS |
|
|
Correction items finished. Final walkthrough passed.
|
FIR14-00103
| INSP-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 4:20:24 PM | P | PASS |
|
|
UG fire supply line permit final approved.
|
FIR14-00708
| INSP-Sprinkler Rough-in/Hydro | 1/16/2015 | 1/16/2015 | 1/16/2015 3:52:46 PM | A | PART |
|
|
Cover inspection for 3rd and 2nd floor E wing wet system at living units only- Completed with reviewed as-builts to match field installation per agreement. Need to adjust tenting at the 2" main 3rd floor NW end, noted three branchlines 2nd floor which do not correlate to the actual install. Okayed for 3rd floor cover, 2nd okayed pending accurate drawings.
|
BLD14-03663
| FIRE-Final Inspection | 1/15/2015 | 1/16/2015 | 1/16/2015 3:45:58 PM | A | PASS |
|
|
Scope of permit work completed. Fire life safety inspection passed.
|
FIR14-00683
| INSP-Sprinkler Rough-in | 1/15/2015 | 1/16/2015 | 1/16/2015 12:07:54 PM | P | CANC |
|
|
BLdg J dry and partial wet Please call Leroy 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
BLD15-00084
| FIRE-Final Inspection | 1/15/2015 | 1/16/2015 | 1/16/2015 11:28:10 AM | A | PASS |
|
|
Life safety inspection passed. Fire extinguishers to be provided with a current re-certification today as agreed.
|
FIR15-00028
| INSP-Final Inspection | 1/15/2015 | 1/16/2015 | 1/16/2015 11:04:57 AM | A | PASS |
|
|
Scope of fire alarm work completed and passed functional testing. Permit finaled.
|
FIR14-00889
| INSP-Sprinkler Rough-in | 1/16/2015 | 1/16/2015 | 1/16/2015 7:50:04 AM | A | PART |
|
|
Completed rough-in inspection of the new dry system at the 2nd floor parking garage- items noted include; overspacing between two branchlines west end, missing coverage at the vestibule, provide flexible couplings at riser main between floors, missing forward flow provision at the riser, new outside WF bell needed, revise existing FDC signage.
|