BLD17-03581
| BLD-Foundation | 1/12/2018 | 1/16/2018 | 1/17/2018 7:55:00 AM | P | DEFR |
|
|
Manuel Phone #: ###-####. Foundation placed yesterday 1-15-18.(holiday) Contractor had special inspection.
|
BLD17-02687
| BLD-Final | 1/16/2018 | 1/16/2018 | 1/16/2018 4:14:02 PM | P | FAIL |
|
|
John Phone #: ###-####. Needs to provide guards on stairs.
|
BLD16-01757
| BLD-Ceiling Grid Inspection | 1/16/2018 | 1/16/2018 | 1/16/2018 3:13:11 PM | P | PASS |
|
|
Nathan Phone #: ###-####. Building #300.
|
BLD16-02975
| BLD-Other | 1/16/2018 | 1/16/2018 | 1/16/2018 2:45:13 PM | P | PASS |
|
|
Fire foam.. Call half hour before to meet // Adam or ###-#### Phone #: ###-####
|
BLD16-02975
| BLD-Energy code compliance | 1/16/2018 | 1/16/2018 | 1/16/2018 2:44:58 PM | P | PASS |
|
|
Fire foam.. Call half hour before to meet // Adam or ###-#### Phone #: ###-####
|
BLD16-02975
| BLD-Framing/Rough-in | 1/16/2018 | 1/16/2018 | 1/16/2018 2:44:43 PM | P | PASS |
|
|
Fire foam.. Call half hour before to meet // Adam or ###-#### Phone #: ###-####
|
BLD17-02429
| BLD-Foundation | 1/15/2018 | 1/16/2018 | 1/16/2018 2:10:10 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-02420
| BLD-Wall Bracing | 1/15/2018 | 1/16/2018 | 1/16/2018 2:07:07 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-04637
| BLD-Framing/Rough-in | 1/12/2018 | 1/16/2018 | 1/16/2018 1:46:54 PM | P | PASS |
|
|
Call half hour before to meet // Fred Phone #: ###-####
|
BLD17-03645
| BLD-Final | 1/15/2018 | 1/16/2018 | 1/16/2018 1:33:59 PM | P | CANC |
|
|
Call for access Phone #: ###-#### Inspection requested via web by Richard Evans. Needs plumbing final.
|
BLD16-04474
| BLD-Wall Bracing | 1/16/2018 | 1/16/2018 | 1/16/2018 1:20:05 PM | P | PASS |
|
|
Stan Phone #: ###-####
|
BLD16-04473
| BLD-Wall Bracing | 1/16/2018 | 1/16/2018 | 1/16/2018 1:19:53 PM | P | PASS |
|
|
Stan Phone #: ###-####
|
BLD16-04472
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 1:19:41 PM | P | PASS |
|
|
Manuel Phone #: ###-####
|
BLD16-04470
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 1:19:29 PM | P | PASS |
|
|
Manuel Phone #: ###-####
|
BLD17-03581
| BLD-Energy code compliance | 1/16/2018 | 1/16/2018 | 1/16/2018 1:00:36 PM | P | CANC |
|
|
Late PM if possible foundation insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
|
BLD17-02156
| BLD-Conference | 1/16/2018 | 1/16/2018 | 1/16/2018 11:39:25 AM | P | DONE |
|
|
Bruce Phone #: ###-####
|
BLD17-03716
| BLD-Wall Bracing | 1/12/2018 | 1/16/2018 | 1/16/2018 11:24:18 AM | A | PASS |
|
|
Jim Phone #: ###-####
|
BLD17-04638
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 11:10:27 AM | P | CANC |
|
|
Pat Phone #: ###-####
|
BLD17-04638
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 11:10:19 AM | P | PASS |
|
|
Chris Phone #: ###-####
|
BLD17-03125
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 11:10:08 AM | P | CANC |
|
|
Pat Phone #: ###-####
|
BLD17-03125
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 11:10:00 AM | P | PASS |
|
|
Chris Phone #: ###-####
|
BLD17-03496
| BLD-Footing | 1/16/2018 | 1/16/2018 | 1/16/2018 10:45:21 AM | A | PASS |
|
|
Concrete is scheduled for 10:30 Phone #: ###-#### Inspection requested via web by kevin debelloy. Footing for new drive thru window.
|
BLD17-04138
| BLD-Footing | 1/12/2018 | 1/16/2018 | 1/16/2018 9:53:22 AM | A | PART |
|
|
Pat Phone #: ###-####
|
BLD17-02419
| BLD-Footing | 1/15/2018 | 1/16/2018 | 1/16/2018 9:27:09 AM | A | PASS |
|
|
Interior footings, concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-04588
| BLD-Framing/Rough-in | 1/12/2018 | 1/16/2018 | 1/16/2018 9:13:05 AM | A | PASS |
|
|
spence larsen Phone #: ###-####. Interior steel stud framed walls only ok. A plumbing permit will be required for new fixture in breakroom.
|
BLD17-04120
| BLD-Footing | 1/15/2018 | 1/16/2018 | 1/16/2018 8:50:56 AM | A | PART |
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD17-03581
| BLD-Energy code compliance | 1/16/2018 | 1/16/2018 | 1/16/2018 7:49:08 AM | A | CANC |
|
|
Late AM if possible. Foundation insulation. Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
|