BLD19-03650
| BLD-Final | 1/16/2020 | 1/16/2020 | 1/16/2020 3:25:19 PM | P | PART |
|
|
zach Phone #: ###-#### ok for temp occ will need to finish doors
|
BLD19-01946
| BLD-Concrete | 1/15/2020 | 1/16/2020 | 1/16/2020 10:39:45 AM | A | PASS |
|
|
rebar basement walls- Dustin Phone #: ###-####
|
BLD19-01927
| BLD-Ceiling Grid Inspection | 1/15/2020 | 1/16/2020 | 1/16/2020 10:18:13 AM | A | PASS |
|
|
Cover inspection for level 5, West and Northwest corridors and offices. Phone #: ###-#### Inspection requested via web by Sam Reading
|
BLD19-03506
| BLD-Footing | 1/15/2020 | 1/16/2020 | 1/16/2020 9:02:09 AM | A | PART |
|
|
Please call 15 minutes prior so that we can ensure access and that we will be there. Rebar for footings again. They had the rebar in place today. The contractor will be there tomorrow morning 1/16 as well to go over their process as the concrete will be placed in phases and will affect the rebar placement. Phone #: ###-#### Inspection requested via web by Erik Hagen first set of ftgs under ext basement walls ok
|