Inspections for the day of: Wednesday, January 17, 1996.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Lightfoot
TitleMEC-STR/MEC INSPECTOR
Phone #794-9463
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC95-01369 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AM FAIL
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
MEC95-01369 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AM FAIL
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
MEC96-00167 INSP - Framing/ Rough-in1/17/19961/17/19961/17/1996 12:00:00 AM PASS
/ / 337 - GP -OK GAS PIPING RGHN-OK ROUGH
MEC96-00167 INSP - Framing/ Rough-in1/17/19961/17/19961/17/1996 12:00:00 AM PASS
/ / 337 - GP -OK GAS PIPING RGHN-OK ROUGH
MEC96-00189 INSP - Rough-in & Gas Pressure1/16/19961/17/19961/17/1996 12:00:00 AMAPART
01/16/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED GP -OK GAS PI
MEC96-00190 INSP - Framing/ Rough-in1/16/19961/17/19961/17/1996 12:00:00 AMANH
01/16/96 337 - INSTALLED 2 UNITS HEATERS, GAS PIPING, VENTING AND INSTAL UGA -UNABLE TO GAIN ACCESS-LEFT NOTC
MEC95-01451 INSP - Framing/ Rough-in1/16/19961/17/19961/17/1996 12:00:00 AMAPASS
01/16/96 337 - KATHY WILL CALL TO SET UP A TIME RGHN-OK ROUGH IN 2nd 3rd FLOORS ONLY
MEC95-01804 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - REINSPECTION FNL -OK FINAL
MEC95-01804 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - REINSPECTION FNL -OK FINAL
MEC95-01816 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPFAIL
01/17/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
MEC95-01816 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPFAIL
01/17/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
MEC95-01961 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPFAIL
01/17/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
MEC95-01961 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPFAIL
01/17/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
MEC95-02242 INSP - Framing/ Rough-in1/17/19961/17/19961/17/1996 12:00:00 AMPNR
01/17/96 337 - THIS IS FOR THE HOOD CORR-CORREC-CALL FOR REINSP WHEN COMPLETED HOOD IS NOT READY
MEC96-00084 INSP - Gas pressure test1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - REINSPECTION GP -OK GAS PIPING
MEC96-00150 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - FNL -OK FINAL
MEC96-00150 INSP - Final1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - FNL -OK FINAL
MEC96-00172 INSP - Gas pressure test1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - REINSPECTION GP -OK GAS PIPING
MEC96-00175 INSP - Framing/ Rough-in1/17/19961/17/19961/17/1996 12:00:00 AMPPART
01/17/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED CORRECTIONS NOT MADE GP -OK GAS PIPING
MEC96-00180 INSP - Framing/ Rough-in1/17/19961/17/19961/17/1996 12:00:00 AMPPASS
01/17/96 337 - THIS WILL BE READY AT 2:00 TODAY FNL -OK FINAL