FIR05-00404
| INSP-Sprinkler Rough-in | 1/17/2006 | 1/17/2006 | 1/17/2006 3:49:40 PM | P | PART |
|
|
B and D third floors are ok to cover. The ceiling has been installed in unit C without a cover inspection for the sprinkler piping. I told the general contractor the ceiling would need to come out for this inspection.
|
BLD05-02382
| FIRE-Final Inspection | 1/13/2006 | 1/17/2006 | 1/17/2006 3:43:02 PM | P | PASS |
|
|
Life safety finaled
|
FIR05-00600
| INSP-Sprinkler Rough-in | 1/17/2006 | 1/17/2006 | 1/17/2006 3:20:02 PM | P | PASS |
|
|
underground supply piping is ok to cover
|
FIR05-00542
| INSP-Supply line flush | 1/16/2006 | 1/17/2006 | 1/17/2006 2:14:50 PM | A | CANC |
|
|
No time for inspection. Per Brian it will be called in for tomorrow.
|
FIR05-00784
| INSP-Sprinkler Rough-in | 1/17/2006 | 1/17/2006 | 1/17/2006 1:46:40 PM | P | PASS |
|
|
Sprinkler piping is ok to cover
|
BLD05-02924
| FIRE-Final Inspection | 1/17/2006 | 1/17/2006 | 1/17/2006 1:28:52 PM | P | FAIL |
|
|
No inspection performed since the first item to be inspected failed which was the smoke evac system. It appears to be missing from the new tenant space. Fire extinguishers need tagged as well.
|
FIR05-00876
| INSP-Sprinkler Rough-in | 1/17/2006 | 1/17/2006 | 1/17/2006 12:46:59 PM | P | FAIL |
|
|
Need to add on upright head just to the west of the main entry and fix all of the falling insulation and backing.
|
BLD05-02014
| FIRE-Final Inspection | 1/13/2006 | 1/17/2006 | 1/17/2006 12:15:21 PM | A | PART |
|
|
A temporary occupancy was given with Dave Hannemans permission until the revised fire alarm plans are approved. Sprinkler permit needs finaled. Life safety will be ok to final when both fire permits are finaled and the new door has closer and seals.
|
FIR05-00676
| INSP-Final Inspection | 1/17/2006 | 1/17/2006 | 1/17/2006 12:14:20 PM | P | PART |
|
|
A temporary occupancy was given with Dave Hannemans permission until the revised fire alarm plans are approved. Pull stations and a/v's as installed work.
|
FIR05-00648
| INSP-Final Inspection | 1/17/2006 | 1/17/2006 | 1/17/2006 12:11:48 PM | P | PART |
|
|
A temporary occupancy was given until the fire alarm permit is approved. This permit needs finaled as well if correction have been made.
|
BLD05-03041
| FIRE-Final Inspection | 1/13/2006 | 1/17/2006 | 1/17/2006 11:41:03 AM | P | FAIL |
|
|
One sprinkler pendant is overspaced at the south end of the parts/storage area.
|
BLD05-03051
| FIRE-Conference | 1/12/2006 | 1/17/2006 | 1/17/2006 11:03:34 AM | A | DONE |
|
|
This project has exiting issues which include door swing, exit hardware, exit signs and emergency lighting in the building and at the exit discharge. Also need one more fire extinguisher. Threshold at exit door is nearly 2" high.
|
BLD04-02149
| FIRE-Final Inspection | 1/13/2006 | 1/17/2006 | 1/17/2006 10:23:01 AM | A | FAIL |
|
|
###-#### SCOTT NOTE: PLEASE SEE HIM OR CALL No one on the fourth floor knew anything about the job and I left a message on scotts voice mail
|
BLD05-02729
| FIRE-Final Inspection | 1/13/2006 | 1/17/2006 | 1/17/2006 9:45:37 AM | A | PASS |
|
|
Life safety finaled
|
FIR05-00667
| INSP-Sprinkler Rough-in/Hydro | 1/16/2006 | 1/17/2006 | 1/17/2006 9:26:57 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 1/16/2006 at 2:23:15 PM. Contact: ###-####.
|
FIR05-00465
| INSP-Sprinkler Rough-in/Hydro | 1/16/2006 | 1/17/2006 | 1/17/2006 9:26:43 AM | A | PART |
|
|
See city approved plans for areas inspected and areas left to inspect
|
FIR05-00864
| INSP-Conference | 1/17/2006 | 1/17/2006 | 1/17/2006 12:00:00 AM | P | CANC |
|
|
mitch; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|