FIR11-00365
| INSP-Sprinkler Rough-in/Hydro | 1/17/2012 | 1/17/2012 | 1/20/2012 10:16:00 AM | P | NR |
|
|
Follow up rough-in inspection of System 8 Mechanical and Sub-Fab Phone #: ###-#### >> Inspection requested via web by Alicia Pauley *NOTE* Previous correction notice items dated 1/12 are incomplete- no change from last visit.
|
FIR11-00483
| INSP-Sprinkler Rough-in | 1/17/2012 | 1/17/2012 | 1/18/2012 5:58:56 PM | P | PART |
|
|
C/N items include missing coverage below stairway at the concealed space, obstructed pendent heads at two restrooms, need to provide coverage at combustible concealed spaces or meet allowable exceptions per NFPA 13, plans do not show pendent heads at the equipment bay area.
|
FIR11-00602
| INSP-Final Inspection | 1/17/2012 | 1/17/2012 | 1/17/2012 1:35:55 PM | P | PASS |
|
|
Scope of permit work passed final walkthrough.
|
FIR11-00511
| INSP-Final Inspection | 1/12/2012 | 1/17/2012 | 1/17/2012 1:34:53 PM | A | PASS |
|
|
Fire alarm work passed inspection. Two added SD in the corridor per red-lines okayed.
|
FIR11-00483
| INSP-Conference | 1/17/2012 | 1/17/2012 | 1/17/2012 1:33:23 PM | A | DONE |
|
|
Regarding location of the wall post indicator control valve.
|