ESC13-00747
| General Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 1:59:49 PM | | CANC |
|
|
Cancelled due to meeting obligations. Rescheduled for Tuesday 1/21/2014
|
ESC13-00144
| General Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 11:43:24 AM | | PEND |
|
|
Lots of unvegetated/disturbed area remains. No activity. Some of project within ACHD right of way - potentially new road. No changes since prior inspection.
|
ESC13-01279
| Site Preparation | 1/16/2014 | 1/17/2014 | 1/17/2014 11:21:52 AM | P | PASS |
|
|
Chad Phone #: ###-####
Pre-con meeting with the following: ESC division and PW Grading Jason Taylor. 1. Warner Construction 2. Hunter Homes 3. Syman Company 4. TO Engineers 5. Strata Geotech
Discussed project and conditions of ESC permit and scope of work. Fill material initially to be trucked in from JUMP. All BMPs and construction entrance must be installed before shipments.
No disturbance of wetland area allowed, keep 50 foot buffer designated.
Inspection of silt fence BMPs and SWPPP binder found them satisfactory.
Project will begin over the next week and proceed in 100x100 ft phases.
Warner Construction stated a sweeper will be onsite to address trackout to Eckart.
Approved for construction.
|
ESC13-00230
| Random Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:49:04 AM | P | PASS |
|
|
Berm has been built on west end of central area in addition to wattles lining the sidewalk Should contain and filter runoff. DI bags exchanged. Whole square was swept on 1/16. Sweeping service is marginal. Site has been cleaned up and additional protection added. No further corrections at this time.
|
ESC13-00458
| Aging Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:44:40 AM | | PASS |
|
|
Finaled.
|
ESC13-00458
| DOC - Permit Finaled | 1/17/2014 | 1/17/2014 | 1/17/2014 9:44:18 AM | P | PASS |
|
|
House complete and landscaped. ESC permit conditions satisfied.
|
ESC14-00022
| General Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:37:41 AM | | PASS |
|
|
No activity. Project started prior to City annexation. Now permited through City. Developer to notify ESC division when project will resume. No corrections at this time.
|
ESC13-01064
| Tracking Control | 1/15/2014 | 1/17/2014 | 1/17/2014 9:32:16 AM | A | PASS |
|
|
Sweeper did sweep around corner and alley. Much of the dirt has been removed though not a perfect job. Brighton Homes did make requested correction so approved at this time.
|
ESC13-00974
| General Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:30:47 AM | | PASS |
|
|
No activity. Winter shutdown. No corrections at this time.
|
ESC13-00581
| Aging Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:19:06 AM | | PASS |
|
|
Finaled.
|
ESC13-00581
| DOC - Permit Finaled | 1/17/2014 | 1/17/2014 | 1/17/2014 9:18:49 AM | P | PASS |
|
|
House complete and landscaped. BLD permit finaled. ESC conditions satisfied.
|
ESC13-00582
| Aging Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:18:17 AM | | PASS |
|
|
Finaled.
|
ESC13-00582
| DOC - Permit Finaled | 1/17/2014 | 1/17/2014 | 1/17/2014 9:18:02 AM | P | PASS |
|
|
House complete and landscaped. BLD permit finaled. ESC conditions satisfied.
|
ESC13-00671
| Aging Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 9:00:19 AM | | PASS |
|
|
Finaled.
|
ESC13-00671
| DOC - Permit Finaled | 1/17/2014 | 1/17/2014 | 1/17/2014 9:00:02 AM | P | PASS |
|
|
Pool installation complete and stabilized. ESC conditions satisfied.
|
ESC13-00892
| Tracking Control | 1/15/2014 | 1/17/2014 | 1/17/2014 8:46:37 AM | A | PASS |
|
|
Check to see if road in front of site is swept and construction entrance replenished.
Road was swept 1/15 as requested. Some sediment and sand from winter road service remains, but is improved.
Construction entrance turned over and refilled.
Discussed schedule with RP Mark and Riley in job trailer. Permit posted and washouts in use.
|